Court: SUPREME JUDICAL COURT OF MASSACHUSETTS
Citation: 423 Mass. 200
Parties: Sutton Corporation vs. Metropolitan District
Commission.
County: Middlesex
Hearing Date: March 6, 1996
Decision Date: July 16, 1996
Judges: Liacos, C.J., Wilkins, Abrams, Lynch, & Greaney, JJ.
Middlesex. Civil action commenced in the Superior Court Department on April 20,
1982. The case was heard by James F. McHugh, III, J., on a master's report.
After review by the Appeals Court, the Supreme Judicial Court granted leave to
obtain further appellate review.
As Amended.
Harvey B. Heafitz (Carol McKenna with him) for the plaintiff.
Christopher W. Morog, Assistant Attorney General (Jason Barshak & James A.
Sweeney, Assistant Attorneys General, with him) for the defendant.
Hugh J. Gorman, III, & Joel Lewin for Utility Contractors Association of
New England, amicus curiae, submitted a brief.
Joseph M. Corwin & Sally A. Corwin for Associated Subcontractors of
Massachusetts, Inc., amicus curiae, submitted a brief.
Joes Lewin & Hugh J. Gorman, III, for Associated General contractors of
Massachusetts, Inc., & another, amici curiae, submitted a brief.
Present: Liacos, C.j., Wilkins, Abrams, Lynch, & Greaney, JJ.
The opinion of the court was delivered by: Lynch
Public Works, Extra work. Contract, Public works, Modification, Performance and
breach, Damages. Practice, Civil, Master: findings. Damages, Breach of
contract, Interest. Interest. Constitutional Law, Referendum. Words,
"Changed conditions."
LYNCH, J. Sutton Corporation (Sutton) brought this action against the
Metropolitan District Commission (MDC) in April, 1982, for damages relating to
site preparation work done on the replacement of the General Lawrence Bridge
(bridge) in Medford. *fn1 A master was appointed
under Mass. R. Civ. P. 53, as amended, 386 Mass. 1237 (1982), who issued a
report containing extensive findings of fact and rulings of law. A Superior
Court judge adopted the master's report in its entirety and awarded Sutton
$255,504.61 plus $346,903.72 in interest. The MDC appealed from the judgment;
Sutton cross appealed. The Appeals Court reversed the decision of the Superior
Court. Sutton Corp. v. Metropolitan Dist. Comm'n, 38 Mass. App. Ct. 764, 652
N.E.2d 627 (1995). We granted Sutton's application for further appellate review
and now affirm the decision of the Superior Court. *fn2
A. Facts. We recite the significant facts as found by the master.
*fn3 Sutton bid for and was awarded a contract
with the MDC to conduct site preparation as part of the replacement of the
bridge. As part of its contract, Sutton was responsible for the installation of
sand drains on the site of the bridge. Sutton contracted with Vibroflotation
Foundation Company for the use of Vibroflotation's patented system of sand
drain installation utilizing the "Dutch Bailor" method, which was one
of the methods sanctioned in the contract specifications.
*fn4
Sutton agreed to charge $3 per linear foot for a total of 141,362 linear feet
of sand drains. Sutton estimated that it would take approximately twenty
minutes to install each of 1,570 sand drains over a period of thirty-five
working days for a total cost of $424,086.
Sutton began installing trial sand drains on April 13, 1981, and immediately
encountered a multitude of problems. Use of the "Dutch Bailor"
method, as designed, resulted in sand drains that did not meet contract
specifications. In attempts to explain these problems, on-site observers
hypothesized that either the clay material in one of the layers of the soil was
overcompacted or the clay in another layer contained more gravel than
anticipated. Everyone agreed that the conditions at the site were unusual and
that the resulting sand drains were unacceptable. On April 24, 1981, after two
weeks of failed attempts to improve the situation, Sutton stopped installing
sand drains. *fn5
By a letter dated April 27, 1981, Sutton advised the MDC that it had
encountered a "changed condition" within the scope of G. L. c. 30,
Sectionn 39N (1994 ed.), and requested permission to use a substitute system
for compacting the soil. Sutton conducted some successful tests of the
substitute "wick drain" system (which was paid for by the MDC), but
ultimately the MDC declined to authorize its use. *fn6 Eventually, Sutton resumed work using a highly-modified
Dutch Bailor system. With the new system, Sutton was able to install sand
drains acceptable to the MDC, but only at much greater cost and time than
anticipated. *fn7
As a result of the sand drain installation, a significant amount of
"spoils material" accumulated on the site. *fn8 Because the spoils material did not meet contract
specifications for ground cover, the MDC required Sutton either to mix it with
other material to bring it within contract specifications or to move the
material offsite and replace it with soil that complied with the contract.
Sutton asked instead to move the material to the preload area, another portion
of the construction site. The MDC declined. Sutton then chose to remove the
spoils material and replace it with "gravel borrow," for a total cost
of $153,094.
B. Changed condition. Sutton first argues that it is entitled to an equitable
adjustment under the changed conditions provision of the contract. The Superior
Court judge adopted the master's rulings that: (1) there was a "changed
condition" within the meaning of G. L. c. 30, Section 39N; and (2) Sutton
satisfied the procedural requirements for an equitable adjustment claim under
the "changed conditions" provision of the contract.
*fn9 The MDC argues, first, that there was no
changed condition. In the alternative it argues that, even if there was a
changed condition, Sutton's claims are barred because they fall under the
purview of the "extra work" provision of the contract (Article XVIII)
and Sutton failed to follow the detailed procedural prerequisites for such a
claim. *fn10 It was on this latter ground that
the Appeals Court reversed the decision of the Superior Court and ruled in the
MDC's favor. 38 Mass. App. Ct. at 760.
We begin with the general rule that "contractor's invocation of remedies
available under either the contract or applicable statutes such as G. L. c. 30,
Section 39N, must be addressed by the public agency in good faith. Glynn v.
Gloucester, 9 Mass. App. Ct. [454, 460-461 (1980) (Glynn I)]." Glynn v.
Gloucester, 21 Mass. App. Ct. 390, 397, 487 N.E.2d 230 (1986) (Glynn II). Here,
Sutton followed the procedures set out in Section 39N (and incorporated in the
contract as part of Article XIX); once Sutton discovered what it believed to be
a changed condition, it ceased operations and notified the MDC by letter
seeking an equitable adjustment. The MDC does not dispute that Sutton fulfilled
the procedural prerequisites of Section 39N.
The master found that, in the course of the sand drain installation, Sutton had
experienced a "Type II" changed condition, because "the site
conditions [were] substantially in conformance with the contract documents, but
the installation system specified did not perform as anticipated."
*fn11 The Appeals Court ruled that the
master's conclusion was "incorrect as matter of law" because it
relied on the failure of the installation system rather than the soil
conditions, Sutton Corp. v. Metropolitan Dist. Comm'n, supra at 767 n.2, but
went on to conclude that "Sutton experienced a changed condition under
Section 39N, since the [master's] subsidiary findings support the conclusion
that the actual soil conditions differed radically from those described in the
contract plans." Id.
We agree that Sutton experienced a changed condition within the meaning of the
statute, but for slightly different reasons than either the master or the
Appeals Court. The Appeals Court correctly criticizes the master's report for
improperly focusing on the performance of the equipment, not the actual
physical conditions, as required by the statute. G. L. c. 30, Section 39N. But
the Appeals Court improperly focuses on the description of the conditions set
out in the contract plans. Id. Where the actual subsurface conditions differ
substantially from those conditions "ordinarily encountered and generally
recognized as inherent in work of the character provided for in the plans and
contract documents," G. L. c. 30, Section 39N, there is a changed
condition under the meaning of the statute, whether or not the conditions
differ from the contract specifications. Thus, contrary to the MDC's
assertions, the Federal "Type II" changed condition is explicitly
part of Massachusetts law, as demonstrated by both the text of the statute and
regulations promulgated pursuant to the statute. *fn12
The master's subsidiary findings support the conclusion that subsurface
conditions at the construction site differed substantially from those
"ordinarily encountered and generally recognized as inherent" in the
installation of sand drains by the methods specified in the contract. G. L. c.
30, Section 39N. The difference in the conditions caused "a change in the
construction methods required for the performance of the work which result[ed]
in an increase . . . in the cost of the work," see Id., a conclusion also
supported by the master's findings. *fn13
The Appeals Court concluded that Sutton forfeited its claim for an equitable
adjustment by failing to follow the procedures for an extra work claim under
Article XVIII of the contract. We disagree. Section 39N mandates that its
provisions be included in public works construction contracts. It provides a
specific procedure and remedy for the contractor encountering differing
subsurface or latent physical conditions. Article XVIII, on the other hand,
applies to "extra work," rather than work required by the contract.
The unexpected soil condition encountered by Sutton required it to modify its
construction methods and incur significant additional expense in order to
complete the contractually required work. Such modifications and additional
expense do not constitute "extra work" within the meaning of Article
XVIII. Cf. Lawrence-Lynch Corp. v. Department of Envtl. Management, 392 Mass.
681, 682-683, 467 N.E.2d 838 (1984). *fn14
The cases cited by the MDC are not to the contrary. It is true that contractors
seeking to recover payment in excess of the contract price must follow the
procedures set out in the contract. See Lawrence-Lynch Corp. v. Department of
Envtl. Management, supra at 684-685, 686; State Line Contractors, Inc. v.
Commonwealth, 356 Mass. 306, 317-319, 249 N.E.2d 619 (1969); Marinucci Bros.
& Co. v. Commonwealth, 354 Mass. 141, 144-145, 235 N.E.2d 783 (1968);
Chiappisi v. Granger Contracting Co., 352 Mass. 174, 177-178, 223 N.E.2d 924
(1967); Lewis v. Commonwealth, 332 Mass. 4, 5-7, 122 N.E.2d 888 (1954); Glynn
II, supra at 394-395; Commonwealth, 332 Mass. 4, 5-7 (1954); Glynn II, supra at
394-395; Skopek Bros. v. Webster Hous. Auth., 11 Mass. App. Ct. 947, 416 N.E.2d
1006 (1981); D. Federico Co.v. Commonwealth, 11 Mass. App. Ct. 248, 252-253,
415 N.E.2d 855 (1981). In those cases, recovery was denied when the contractor
failed to give timely notice of its claim to the public agency. Without such
notice, the contracting authority was unable to monitor the additional expenses
incurred by the contractor. Here, on the contrary, Sutton met the procedural
requirements for a claim under Section 39N: it provided timely written notice
of its claim to the MDC. As the master found, the MDC was aware throughout the
project of Sutton's additional expense. *fn15
Furthermore, there was no evidence or finding that the MDC was prejudiced in
any way by the lack of an itemized statement of damages. Therefore, we conclude
that the MDC's refusal to pay Sutton's additional sand drain installation
expenses was improper. *fn16
C. Substitution. Sutton argues that the MDC should have approved the use of
a substitute method of soil compaction under G. L. c. 30, Section 39M (b) (1994
ed.). *fn17 The master ruled that "the
MDC should have permitted Sutton to substitute the Alidrain or wick system as
an 'or equal' system pursuant to Mass. G. L. c. 30, Section 39M and the failure
or refusal by the MDC to allow the substitution was a breach of its contract
with Sutton."
The master's ruling was incorrect. The wick drain system is not equivalent to
the Dutch Bailor method for purposes of substitution under G. L. c. 30, Section
39M (b). Even if we assume that both systems are "materials" within
the meaning of G. L. c. 30, Section 39M (e), a proposition not free from doubt,
they fail at least two of the three requirements for a substitute. First, the
wick drain system is not "at least equal" to the Dutch Bailor method
in either appearance or design. See G. L. c. 30, Section 39M (b) (1). Sand
drains are water-jetted holes filled with sand; wick drains are porous plastic
tubes. The two types of drains are installed by substantially different
methods. In particular, the master found that the installation of sand drains
displaces significantly more material than wick drain installation. Second,
despite the master's contrary conclusion, the wick drain system does not meet
the statutory requirement that it "conform[] substantially, even with
deviations, to the detailed requirements for the item in the . . .
specifications." G. L. c. 30, Section 39M (b) (3). The master found that
the two systems were equal in "quality, durability, strength and
design" and that the wick drain system "achieved the intent of the
specifications" because it performed the same function as the jetted
method. Any difference in appearance was "irrelevant," the master
found, "because the system was installed below ground level and not
visible." The master's ultimate conclusion on the substitution issue is
clearly erroneous as a matter of law in light of the information in the record
and mutually inconsistent with his subsidiary findings about the nature of the
two drain systems. See Melrose Hous. Auth. v. New Hampshire Ins. Co., 402 Mass.
27, 34, 520 N.E.2d 493 (1988). The record does not support the master's finding
that the two systems were equal in design. There are numerous subsidiary
findings detailing the differences in design. In fact, the master's implied
finding that the two systems differ in appearance itself suggests two different
designs. Appearance is a factor set out in the statute and is not irrelevant,
even where the system will not be visible once installed. See John F. Miller
Co. v. George Fichera Constr. Corp., 7 Mass. App. Ct. 494, 496-497, 388 N.E.2d
1201 (1979) (proposed substitute waste piping system in housing construction
project was not equal, even though it complied with State plumbing code).
Finally, to the extent that the finding involves the interpretation of a
statute, it is a conclusion of law and subject to independent judicial review.
Pollock v. Marshall, 391 Mass. 543, 555, 462 N.E.2d 312 (1984), and cases
cited. The contract specifications detail two permissible methods of soil
compaction: jetted sand drains and augered sand drains. Wick drains are not
included. The differences between wick drains and the methods in the contract
are significantly more than deviations; instead, the wick drain system is a
"different animal" entirely. John F. Miller Co. v. George Fichera
Constr. Corp., supra at 497.
The Appeals Court cases addressing this issue support our conclusion. In John
F. Miller Co. v. George Fichera Constr. Corp., supra at 496-498, for example, a
subcontractor attempted to substitute one waste piping system for another. The
proposed system would have changed the size, number, and location of fittings,
pipes, and vents and the materials out of which they were made. Id. at 496. The
court agreed that the proposed system did not meet the requirements of Section
39M (b ), and was, in fact, "a fairly fundamental change of the design and
system prescribed by the specifications." Id. at 497.
*fn18 See also Acmat Corp. v. Daniel
O'Connell's Sons, 17 Mass. App. Ct. 44, 48-49, 455 N.E.2d 652 (1983). Cf. E.A.
Berman Co. v. Marlborough, 11 Mass. App. Ct. 1009, 1010, 419 N.E.2d 319 (1981).
Therefore, we conclude that, while the MDC owes Sutton an equitable adjustment
under the "changed conditions" clause, the MDC did not breach its
contract with Sutton by failing to approve the use of the substitute wick drain
system.
D. Spoils material. We now address the issues raised by Sutton in its cross
appeal. The first issue involves Sutton's extra work claim for the costs of
removing and replacing spoils material. The master ruled that, under the
contract, the MDC had a right to refuse Sutton's request to move the spoils
material to the preload area of the construction site. In addition, the master
ruled, the MDC had the right to require Sutton to remove the spoils material
and replace it with conforming material without extra cost to the MDC.
*fn19
Sutton argues that it is entitled to the additional costs incurred in removing
the spoils material because those costs were a direct result of the MDC's
failure to allow Sutton to use the substitute wick drain system, citing White
Spot Constr. Corp. v. Jet Spray Cooler, Inc., 344 Mass. 632, 635, 183 N.E.2d
719 (1962). Because we have concluded, (infra), that the MDC did not breach the
contract by failing to approve the wick drain proposal, Sutton is not entitled
to damages arising from such a failure. Furthermore, the contract clearly
provides that Sutton was not entitled to recover for the cost of removing and
replacing the spoils material. See note 19, (supra) .
*fn20
E. Damages calculation. The master found that the contract limited Sutton's
damages to those directly related to the installation of the sand drains under
the modified Dutch Bailor method. Consequently, he rejected claims for extended
job overhead, delay, and consequential damages. In so doing, the master relied
on provisions of the contract relating to payment for extra work, including
Article XVIII. *fn21 Although we have
concluded that Article XVIII does not apply to a claim for an equitable
adjustment under Section 39N, we do not thereby automatically reject the
master's approach. Where, as here, there is no contractual or statutory
provision for an appropriate measure of damages after the wrongful denial of an
equitable adjustment, it is reasonable to refer to the contractual damages
formula concerning payment for extra work. Indeed, the MDC's regulations for
settling equitable adjustment claims contain a damages formula nearly identical
to the one contained in the contract and used by the master. 350 Code Mass.
Regs. Section 13.01 (7) (b) (1993). We therefore uphold the master's
calculation of damages as reasonable and in accordance with the appropriate
statutory and contractual provisions.
Sutton argues that it is entitled to a greater measure of damages than the
contract provides because, by denying the claim for an equitable adjustment,
the MDC allegedly committed a "true breach" of the contract.
*fn22 We disagree. A claim for an equitable
adjustment under the changed conditions provision is a claim for relief under
the contract, and is not a "true" breach of contract claim. United
States v. Utah Constr. & Mining Co., 384 U.S. 394, 404-405 n.6, 16 L. Ed.
2d 642, 86 S. Ct. 1545 (1966). Cf. Glynn II, supra at 397-398 (suggesting that,
where agency acts in bad faith, unjustified rejection of proper equitable
adjustment claim might constitute true breach of contract [dictum]). Sutton's
damages, therefore, are limited to those provided by the terms of the contract
and the statutes governing public construction projects.
F. Interest. In its original appeal, the MDC protested the Superior Court's
application of prejudgment interest at the rate of twelve per cent per annum to
Sutton's award. We now examine whether the interest award was proper.
In 1993, the way that interest is calculated in judgments against the
Commonwealth in contract actions was changed. G. L. c. 231, SectionSection 6C,
as amended through St. 1993, c. 110, Section 224, and 6I, inserted by St. 1993,
c. 110 Section 225. Passed as outside sections of an appropriations bill such
interest is now calculated by reference to the coupon issue yield equivalent of
the price for United States treasury bills, capped at ten per cent. The
sections were approved July 19, 1993, but, by St. 1993, c. 110, Section 390,
were made effective July 1, 1993. The statute did not contain an emergency
preamble and did not explicitly state whether it had retroactive effect. The
Superior Court clerk entered final judgment in the case on August 16, 1993.
Interest was calculated at twelve per cent per annum from the date the
complaint was filed (April 20, 1982) until the date of the final judgment.
The MDC argues that the clerk should have applied the new, lower interest rate
to the judgment. Sutton responds that, because it was subject to referendum,
the amended interest statute did not take effect until ninety days after its
enactment, citing art. 48, The Referendum, I, of the Amendments to the
Constitution of the Commonwealth. Because final judgment entered before the
effective date, Sutton argues, the amendment does not apply to this action.
We agree with Sutton that the 1993 amendment does not apply because it became
effective after final judgment was entered. Laws which are subject to
referendum do not take effect until ninety days after passage, unless they are
designated as emergency laws. Art. 48, The Referendum, I. See Mirageas v.
Massachusetts Bay Transp. Auth., 391 Mass. 815, 819-820, 465 N.E.2d 232 (1984).
The MDC argues that this law is not subject to referendum because it
"appropriates money for the current or ordinary expenses of the
commonwealth," which is an excluded subject under the Constitution. Art.
48, The Referendum, III, Section 2. See Mitchell v. Secretary of Admin., 413
Mass. 330, 337, 597 N.E.2d 400 (1992); Powell v. Cole-Hersee Co., 26 Mass. App.
Ct. 532, 535, 529 N.E.2d 1359 (1988). In Mirageas v. Massachusetts Bay Transp.
Auth., supra at 820, we assumed that, barring an effective emergency preamble,
a statute changing the interest rate applied to judgments would be subject to
referendum. The only difference between that case and the one before us is that
the 1993 amendment was attached to an appropriations bill as an outside
section. We have declined to determine the constitutionality of attaching
provisions that do not appropriate funds (outside sections) to appropriation
bills. Mitchell v. Secretary of Admin., supra, quoting Brookline v. The
Governor, 407 Mass. 377, 382, 384, 553 N.E.2d 1277 (1990). The practice, even
if it is constitutional, would not be effective to insulate a legislative
enactment from the operation of art. 48, when that enactment did not pertain to
matters excluded from the referendum process by art. 48. Here, the provisions
of the bill relating to interest in actions against the Commonwealth are not
sufficiently related to appropriations to bring them within the excluded
matters provision of art. 48. *fn23 The
clerk's calculation of interest was correct. *fn24
G. Conclusion. Accordingly, we reject both the MDC's appeals and Sutton's cross
appeals. We conclude that Sutton is entitled to recover the full amount of the
Superior Court judgment. *fn25
Judgment affirmed.
Opinion Footnotes
*fn1 Sutton also initially brought a claim
against Vibroflotation Foundation Company. Geotechnical Engineers, Inc.;
Somerville Engineers, Inc.; and United States Fidelity and Guaranty Company
were also parties. All of these additional parties were dismissed prior to the
determination of the case on the merits. Sutton Corp. v. Metropolitan Dist.
Comm'n, 38 Mass. App. Ct. 764, 764 n.1, 652 N.E.2d 627 (1995).
*fn2 We acknowledge the amicus briefs of Utility
Contractors Association of New England, Inc., Associated Subcontractors of
Massachusetts, Inc., and Associated General Contractors of Massachusetts, Inc.,
and Construction Industries of Massachusetts, Inc., on behalf of the
plaintiff.
*fn3 We agree with the Appeals Court that the
parties' objections were not sufficient to raise a challenge to the master's
subsidiary findings of fact. See Sutton Corp. v. Metropolitan Dist. Comm'n,
supra at 765-766. Therefore, we accept those findings "unless they are
clearly erroneous, mutually inconsistent, unwarranted by the evidence before
the master, or are otherwise tainted by error of law. Mass. R. Civ. P. 53 (h)
(1), as amended, 386 Mass. 1237 (1982)." Bishay v. Foreign Motors Inc.,
416 Mass. 1, 3 n.4, 616 N.E.2d 96 (1993).
*fn4 The master found: "A sand drain is a
vertical hole in the ground, approximately 12 [inches] in width and, in this
instance, 90 to 100 [feet] in depth. . . . The 'Dutch Bailor' or 'jetted'
method of sand drain installation involves the use of a dropping head or bailor
which pulsates in a vertical manner as it is lowered into the ground. A high
pressure jet of water is sprayed into the hole liquefying the earth; the
earthen materials float to the surface in suspension as the water level in the
hole rises, ultimately flowing out onto the work area surface. . . . Once the
water drains from the hole, the hole is filled with sand. . . . The purpose of
the sand drains is to provide a route for the moisture that is trapped in the
soil below to percolate to the surface, thus permitting quicker compaction of
the soil."
*fn5 The master found that "the resident
engineer noted in his Project Diary entry for that day as follows: 'there is a
definite problem with the existing conditions.'"
*fn6 The master found: "The wick or
Alidrain system involves inserting an oblong shaped piece of plastic tubing
into the ground by means of a long mandrel. A jet spray of water is used to
assist in clearing a path through the earth for the mandrel. The plastic tube
remains in the hole after the mandrel is withdrawn. There are numerous pores or
openings in the plastic tube or 'wick' through which the moisture in the soil
seeps and rises to the surface, thus performing the same function as the sand
drains in facilitating the consolidation of the soil. The wick system was not
among the drainage systems included in the contract specifications."
*fn7 The master found that "representatives
of the MDC . . . were well aware throughout the course of the sand drain
installation of the length of time that was involved in the installation of the
sand drains, as a result of the modifications to the Dutch Bailor System, and
that the attendant delay would result in increased expense to Sutton."
*fn8 The spoils material was a byproduct of sand
drain installation: the jetted water used in creating the sand drains carried
soil, residue clay, dirt, and gravel out of the hole being created to settle
elsewhere on the construction site.
*fn9 General Laws c. 30, Section 39N (1994 ed.),
provides, in relevant part: "Every [public works construction] contract .
. . shall contain the following paragraph in its entirety . . . :
"If, during the progress of the work, the contractor or the awarding
authority discovers that the actual subsurface or latent physical conditions
encountered at the site differ substantially or materially from those shown on
the plans or indicated in the contract documents either the contractor or the
contracting authority may request an equitable adjustment in the contract price
of the contract applying to work affected by the differing site conditions. A
request for such an adjustment shall be in writing and shall be delivered by
the party making such claim to the other party as soon as possible after such
conditions are discovered. Upon receipt of such a claim from a contractor, or
upon its own initiative, the contracting authority shall make an investigation
of such physical conditions, and, if they differ substantially or materially
from those shown on the plans or indicated in the contract documents or from
those ordinarily encountered and generally recognized as inherent in work of
the character provided for in the plans and contract documents and are of such
a nature as to cause an increase or decrease in the cost of performance of the
work or a change in the construction methods required for the performance of
the work which results in an increase or decrease in the cost of the work, the
contracting authority shall make an equitable adjustment in the contract price
and the contract shall be modified in writing accordingly" (emphasis
added).
*fn10 Article XVIII of the contract
provides:
"The Contractor shall do any work not herein otherwise provided for, when
and as ordered in writing by the Engineer, or his agents especially thereto
authorized in writing, and shall, when requested by the Engineer so to do,
furnish itemized statements of the cost of the work ordered and give the
Engineer access to accounts, bills and vouchers relating thereto. If the
Contractor claims compensation for extra work not ordered as aforesaid, or for
any damage sustained, he shall, within one week after the beginning of any such
work or of the sustaining of any such damage, make a written statement of the
nature of the work performed or damage sustained to the Engineer, and shall on
or before the fifteenth day of the month succeeding that in which any such
extra work shall have been done or any such damage shall have been sustained,
file with the Engineer an itemized statement of the details and amount of such
work or damage, and unless such statements shall be made as so required his
claim for compensation shall be forfeited and invalid, and he shall not be
entitled to payment on account of any such work or damage. The cost of extra
work shall not include any general or indirect overhead charges and shall be
determined by such method of compensation as approved by the and provided for
in the Proposal. Any equipment employed by the Contractor for use in extra work
shall be of such amount and at such rental rates as the Engineer approves. The
determination of the Engineer shall be final upon all questions of the amount
and value of extra work."
*fn11 The standard changed conditions
provision for Federal contracts "enables the contractor to obtain an
equitable adjustment in price if it encounters 'during the progress of the work
[1] subsurface and/or latent physical conditions at the site materially
differing from those shown on the drawings or indicated in the specifications,
or [2] unknown physical conditions of an unusual nature differing materially
from those ordinarily encountered and generally recognized as inhering . . .'
in the type of work being done." United Contractors v. United States, 177
Ct. Cl. 151, 368 F.2d 585, 594 (Ct. Cl. 1966). See Stock & Grove Inc. v.
United States, 204 Ct. Cl. 103, 493 F.2d 629, 644-645 (Ct. Cl. 1974); Charles
T. Parker Constr. Co. v. United States, 193 Ct. Cl. 320, 433 F.2d 771, 772 n.1
(Ct. Cl. 1970); Kaiser Indus. Corp. v. United States, 169 Ct. Cl. 310, 340 F.2d
322, 324 (Ct. Cl. 1965). A claim for an equitable adjustment under the second
clause of the standard provision is commonly referred to as a "Type
II" changed condition claim.
*fn12 Title 350 Code Mass. Regs. Section 13.01
(1993) provides, in relevant part:
"(1) The Contractor shall, upon encountering differing subsurface or
latent physical conditions, promptly cease operations in the area of such
conditions and notify the Engineer, in writing, describing in full detail the
subsurface or latent physical conditions at the site which he maintains differs
substantially or materially from those shown on the plans or indicated in the
contract documents, or from those ordinarily encountered and generally
recognized as inherent in work of the character provided for in the plans and
contract documents. . . .
"If the finds that such conditions, as have been described in detail by
the Contractor, do exist, and are of such a nature as to cause an increase or
decrease in cost of performance of the work or a change in the construction
methods required for the performance of the work which results in an increase
or decrease in the cost of the work, the shall make an equitable adjustment in
the contract price . . . ." (Emphasis added.)
*fn13 We agree with the master that Sutton
was not required to conduct independent tests of the subsurface conditions at
the site. Demanding such tests would frustrate the policy of G. L. c. 30,
Section 39N.
*fn14 Even if Article XVIII did apply to
Sutton's claim, "to the extent there may be conflict between the expressed
contract and the statutorily required provision, the required provision
controls." Reynolds Bros. v. Commonwealth, 412 Mass. 1, 5, 586 N.E.2d 977
(1992).
*fn15 The MDC had the right, under its
regulations, to request that Sutton furnish itemized statements of costs due to
changed conditions. There is no finding that the MDC ever made such a request.
See 350 Code Mass. Regs. Section 13.01 (6) (1993).
*fn16 Because we conclude that Sutton is
entitled to an equitable adjustment under Section 39N, we need not address the
master's conclusion that Sutton was excused from complying with the itemized
damages provisions of Article XVIII because such compliance would have been
futile. Cf. D. Federico Co. v. Bedford Redevelopment Auth., 9 Mass. App. Ct.
141, 143, 399 N.E.2d 1103 (1980).
*fn17 General Laws c. 30, Section 39M (1994
ed.), provides, in relevant part:
"(b) Specifications for [public works construction] contracts . . . shall
be written to provide for full competition for each item of material to be
furnished under the contract . . . . Every such contract shall provide that an
item equal to that named or described in the said specifications may be
furnished; and an item shall be considered equal to the item so named or
described if (1) it is at least equal in quality, durability, appearance,
strength and design, (2) it will perform at least equally the function imposed
by the general design for the public work being contracted for or the material
being purchased, and (3) it conforms substantially, even with deviations, to
the detailed requirements for the item in the said specifications. . . .
"(e) The word 'material' as used in this section shall mean and include
any article, assembly, system, or any component part thereof."
*fn18 Sutton seeks to distinguish the result
in John F. Miller Co. v. George Fichera Constr. Corp., 7 Mass. App. Ct. 494,
388 N.E.2d 1201 (1979), on the ground that a finding of the master in that case
supported the court's conclusion. We note, however, that the court may draw its
own conclusions from the master's subsidiary findings. Mass. R. Civ. P. 53 (h)
(1), as amended, 386 Mass. 1237 (1982).
*fn19 The master relied on the following
contract provisions in making his ruling:
"Contamination of material within the drainage blanket at the sand drain
periphery shall be removed and replaced with drainage backfill at no additional
cost. . . .
"The materials jetted or augered from the holes shall be disposed of in a
manner approved by the Engineers. The Contractor shall propose and receive
approval of such methods prior to the work. The working surface shall be
cleaned of all remaining unsuitable materials after drain installation. Such
unsuitable materials include clay or silt lumps or organic matter which, if
left in place, would, in the opinion of the Engineer, create 'silt spots' or
zones of compressibility [or] weakness in connection with placement of
overlying embankment materials.
"Cleaning-Up. All . . . dirt, debris and waste materials caused in the
performance of the work shall be removed from the work areas from time to time
as directed by the Engineer. . . ."
*fn20 Sutton also argues that the master erred
in failing to admit in evidence a 1983 inspector general's report on the MDC,
which includes a discussion of the General Lawrence Bridge construction
project. According to Sutton, the document fit within the public records
exception to the hearsay rule, see Julian v. Randazzo, 380 Mass. 391, 393, 403
N.E.2d 931 (1980), and would have provided evidence that a bridge plan existed
at the time when Sutton was attempting to dispose of the spoils material. Had
the MDC furnished Sutton with such a plan, the master found, the spoils
material could have been relocated to the preload area of the construction
site. Such a relocation presumably would have permitted Sutton to incur less
expense. We conclude that the master did not abuse his discretion in excluding
the inspector general's report, which alludes to, but does not contain a plan
of the bridge replacement design. See Enrich v. Windmere Corp., 416 Mass. 83,
84 n.2, 616 N.E.2d 1081 (1993). In addition, there was no finding that, had a
plan been available, the MDC would have authorized Sutton to relocate the
spoils material to the preload area.
*fn21 The contract sets out the following as
one of the acceptable formulae for calculating "payment for extra
work":
"(1) Actual cost of direct labor
"(2) Actual cost of materials (less salvage value, if any)
"(3) Actual cost of reasonable rental rates for equipment
"(4) 15% of (1), (2) and (3)
"(5) Actual cost of Public Liability Property Damage and Workmen's
Compensation Insurance and payments under Federal Social Security and
Massachusetts Unemployment Compensation acts for subject extra work
"(6) There shall be no allowance made for superintendence, general or
direct overhead charges, nor for the use of small tools and manual
equipment."
*fn22 "When the contract makes provision
for equitable adjustment of particular claims, such claims may be regarded as
converted from breach of contract claims to claims for relief under the
contract." United States v. Utah Constr. & Mining Co., 384 U.S. 394,
404-405 n.6, 16 L. Ed. 2d 642, 86 S. Ct. 1545 (1966). Recovery for such claims
is limited to the remedies provided in the contract. When a particular claim
falls outside the contract, such that it is not redressable under specific
contract adjustment provisions, it is a "true" breach of contract
claim that may justify an award of damages. Id. Glynn v. Gloucester, 21 Mass.
App. Ct. 390, 397-398, 487 N.E.2d 230 (1986). Glynn v. Gloucester, 9 Mass. App.
Ct. 454, 461, 401 N.E.2d 886 (1980).
*fn23 The parties did not address, and so we
do not consider whether prejudgment interest is a proper subject for an outside
section of an appropriations bill. See Brookline v. The Governor, 407 Mass.
377, 382 nn.6&7, 553 N.E.2d 1277 (1990).
*fn24 Because we conclude that the amendment
took effect after final judgment in the action, we need not address the
question of its retroactivity. Cf. Mirageas v. Massachusetts Bay Transp. Auth.,
391 Mass. 815, 821 & n.9, 465 N.E.2d 232 (1984); Porter v. Clerk of the
Superior Court, 368 Mass. 116, 330 N.E.2d 206 (1975).
*fn25 Sutton has not appealed from the
master's ruling in MDC's
favor regarding test pile mobilization costs and therefore we do not
address that issue.