Court: SUPREME JUDICIAL COURT OF
MASSACHUSETTS
Citation: 439 MASS. 759 (2003)
Parties: SIEMENS BUILDING TECHNOLOGIES, INC. v. DIVISION
OF CAPITAL ASSET MANAGEMENT, JOHNSON CONTROLS, INC. (JOHNSON CONTROLS); N.B.
KENNEY COMPANY, INC.; AND SUFFOLK
CONSTRUCTION CO., INC.
Decision Date: JULY 16, 2003
Judges: CORDY, J.
Stephen
M. Sheehy for the plaintiff.
Stephen
H. Clark, Assistant Attorney General, for Division of Capital Asset Management.
Peter
J. Gagne, Boston, for N.B. Kenney Company, Inc.
obert
P. Garrity, Boston, for Johnson Controls, Inc., was present but did not argue.
Paul
W. Losordo, Quincy, for Suffolk Construction Co., Inc., was present but did not
argue.
Present: MARSHALL, C.J., GREANEY, IRELAND, SPINA,
SOSMAN, & CORDY, JJ.
Prospective sub‑subcontractor
for state university construction project sought preliminary and permanent
injunctions preventing Commonwealth from using different provider. The Superior Court Department, Suffolk
County, Allan van Gestel, J., denied motion for preliminary injunction. Prospective sub‑subcontractor
appealed. The Supreme Judicial Court,
Cordy, J., held that: (1) Division was not required to use prospective sub‑subcontractor
who had been listed in subcontractor's bid form, and (2) Division was not
required to initiate new public solicitation for bids.
In determining whether to issue
preliminary injunction, the judge initially evaluates in combination the moving
party's claim of injury and chance of success on the merits; if the judge is
convinced that failure to issue the injunction would subject the moving party
to a substantial risk of irreparable harm, the judge must then balance this
risk against any similar risk of irreparable harm which granting the injunction
would create for the opposing party.
Once Division of Capital Asset
Management found that prospective sub‑subcontractor who had been listed
in subcontractor's bid form could not provide automatic temperature control
system that was satisfactory for state university construction project,
Division was not required to initiate new public solicitation of bids for
system; Division was free to direct
general contractor to substitute product and provider that would meet
specifications. M.G.L.A. c. 149, s 44A
et seq.
After being replaced as the proposed
provider of an automatic temperature control system to a public construction
project, Siemens Building Technologies, Inc. (Siemens), sought preliminary and
permanent injunctions preventing the Commonwealth from using a different
provider on the grounds that Siemens's contract and the public bidding laws had
been violated. A judge in the Superior
Court refused to issue the preliminary injunction, and Siemens appealed. We transferred the case to this court on our
own motion, and we affirm the judge's ruling.
1. Background. The facts of
this case are not disputed. In
November, 2000, the Commonwealth's division of capital asset management
(division) solicited bids, pursuant to G.L. c. 149, ss 44A‑44H, for
general contracting and subcontracting work related to the construction of a
new campus center at the University of Massachusetts at Boston
(university). One subcontract required
the provision of a heating, ventilating, and air conditioning (HVAC) system for
the center. The defendant N.B. Kenney
Company, Inc. (Kenney), submitted a bid for the subcontract. As required by G.L. c. 149, s 44F (2),
Kenney listed on its bid form the names of the sub‑subcontractors that it
planned to use. One of these sub‑subcontractors
was Siemens, listed as the provider of the automatic temperature control
system. Siemens was the only company to
submit a bid proposal to Kenney for the system‑‑not surprising, as
Siemens's automatic temperature control systems were used throughout the rest
of the university campus, and the division's project specifications required
that the automatic temperature control system for the campus center interface
with the existing Siemens systems.
On December 14, 2000, the division
received the subcontract bids. Kenney
was awarded the HVAC subcontract. On
January 4, 2001, the division opened the general contract bids. Due to issues unrelated to this litigation,
however, the naming of the general contractor was delayed several months. By the time the division executed the
general contract with the defendant Suffolk Construction Co., Inc. (Suffolk),
it had learned that the existing campus‑wide Siemens automatic
temperature systems were to be replaced with systems manufactured by Johnson [439 Mass. 761] Controls, Inc. (Johnson Controls). (FN2) This meant that the automatic temperature
control system in the new campus center would now need to interface and be
compatible with a Johnson Controls system.
Accordingly, the division revised its specification for the campus
center system to ensure compatibility with the new campus‑wide Johnson
Controls system. It also conducted an
investigation as to *343
whether the system that Siemens had proposed to install could
successfully interface with the Johnson Controls system.
To assist in this endeavor, the
division hired a technical consulting firm specializing in the field. After assessing both Siemens and Johnson
Controls systems, the consultant reported to the division on October 12, 2001,
that "[t]he Siemens [system] is in our technical opinion, unable to meet
specification ... while the [Johnson Controls system] is...." The division adopted the findings in the
consultant's report and instructed the general contractor to change its
automatic temperature control system provider from Siemens to Johnson
Controls. That same day, the division
informed Siemens of the decision by letter, noting that its decision was
"in the best interests of the Commonwealth."
Siemens filed suit on October 25,
2001, against the division, Suffolk, Kenney, and Johnson Controls, alleging
breach of contract and violation of the public bidding law, G.L. c. 149, ss 44A‑44H. When its request for a preliminary
injunction was denied, Siemens petitioned for interlocutory relief pursuant to
G.L. c. 231, s 118, first par., from a single justice of the Appeals Court, who
denied the petition. Siemens then
appealed to the full Appeals Court. We
transferred the case to this court on our own motion.
[1][2][3][4][5] 2. Discussion. The standard that a moving party must meet to obtain a
preliminary injunction is well established:
"[T]he
judge initially evaluates in combination the moving party's claim of injury and
chance of success on the [439 Mass.
762] merits. If the judge is convinced that failure to
issue the injunction would subject the moving party to a substantial risk of
irreparable harm, the judge must then balance this risk against any similar
risk of irreparable harm which granting the injunction would create for the
opposing party. What matters as to each
party is not the raw amount of irreparable harm the party might conceivably
suffer, but rather the risk of such harm in light of the party's chance of
success on the merits." (Footnote
omitted.)
Packaging
Indus. Group, Inc. v. Cheney, 380 Mass. 609, 617, 405 N.E.2d 106
(1980). When a party seeks to enjoin governmental
action, a judge is also "required to determine that the requested order
promotes the public interest, or, alternatively, that the equitable relief will
not adversely affect the public." Commonwealth v. Mass. CRINC, 392 Mass.
79, 89, 466 N.E.2d 792 (1984). In
reviewing a judge's allowance or denial of a preliminary injunction, "[w]e
decide whether the judge applied proper legal standards and whether there was
reasonable support for his evaluation of the factual questions."
Hull Mun. Lighting Plant v. Massachusetts Mun. Wholesale Elec. Co.,
399 Mass. 640, 642, 506 N.E.2d 140 (1987), citing Packaging Indus. Group, Inc. v. Cheney, supra at 615, 405 N.E.2d
106. Where there is no dispute
regarding the facts of the case and no credibility determinations on which we
would defer to the judge, we draw our own conclusions from the evidence in the
record.
We look first to the moving party's
prospects for success on the merits of its legal claim. (FN3)
General Laws c. 149, ss 44A‑44H, sets out the procedure by which
public construction contracts are to be awarded. (FN4) *344
Both general contract bidders and subcontract bidders are subject to
numerous procedural requirements, including the submission of a bid bond
accompanying their bid, G.L. c. 149, s 44B (2), and the use of prescribed
forms, G.L. c. 149, s 44E (2) (general bids);
s 44F (2) (subbids). In
paragraph E of the subbid form, a subbidder must list the names of the sub‑subcontractors
that it will employ [439 Mass. 763] based on bids that it has received
from prospective sub‑subcontractors.
(FN5) G.L. c. 149, s 44F (3),
fourth par. Paragraph F of the subbid
form contains an agreement that "the above list of bids to the undersigned
[subbidder] represents bona fide bids based on the hereinbefore described
plans, specifications and addenda and that, if the undersigned is awarded the
contract, they will be used for the work indicated at the amounts stated, if
satisfactory to the awarding authority."
G.L. c. 149, s 44F (2), par. F.
The requirement that sub‑subcontractors be listed in paragraph E and the
representation by the subbidder that they will be used as long as they are
"satisfactory to the awarding authority" are the only provisions of
the public bidding law that address the status of sub‑subcontractors.
In this case, the provisions of G.L.
c. 149, ss 44A‑44H, were followed.
Kenney, in its subbid for the campus center's HVAC work, listed Siemens
as its automatic temperature control system sub‑subcontractor, and Kenney
was selected as the HVAC subcontractor in accordance with statutory
procedures. Siemens's complaint
regarding the subsequent events is twofold.
First, once Kenney was selected as the HVAC subcontractor, Siemens
contends that the division and Suffolk were contractually obligated to use
Siemens as the automatic temperature control sub‑subcontractor. Second, once the division removed Siemens as
the provider of the campus center system, it was obligated by G.L. c. 149
publicly to solicit new bids for the campus center's automatic temperature
control work.
[6] Neither claim is likely to
succeed. As noted above, the only
requirements established by G.L. c. 149, ss 44A‑44H, regarding sub‑subcontractors
are that they be listed on the subbidder's bid form and that the successful
subbidder agree to use them if they are "satisfactory to the awarding
authority." G.L. c. 149, s 44F
(2), par. F. Nothing in the statute
prevents the awarding authority from determining that a prospective sub‑subcontractor
is not satisfactory and removing it from the contract. (FN6)
There is no merit to Siemens's argument that the division never [439 Mass. 764] determined that Siemens was "not 'satisfactory.' " The consulting report assessing the Siemens
system to determine its compatibility with a campus‑wide Johnson Controls
system concluded that the Siemens system is "unable to meet specification *345.
sections." The division's
acceptance of the report's findings as the basis for its decision to remove
Siemens from the project was the equivalent of a specific finding that Siemens
was not satisfactory. (FN7) The decision was neither "illegal [n]or
arbitrary." Capuano, Inc. v. School Bldg. Comm. of
Wilbraham, 330 Mass. 494, 496, 115 N.E.2d 491 (1953).
[7] Siemens's claim that the
division violated the provisions of G.L. c. 149, ss 44A‑44H, by not
initiating a new public solicitation of bids for the automatic temperature
control system sub‑subcontract once it found the Siemens system not
satisfactory, is equally unavailing.
General Laws c. 149, ss 44A‑44H, set out the process by which
general contracts and subcontracts are to be awarded. There is no provision for the bidding and awarding of sub‑subcontracts
independent of a subcontract.
(FN8) Thus, there was no
applicable provision of G.L. c. 149 for the division to violate. (FN9)
In these circumstances, the motion judge correctly concluded that
Siemens is not a bidder of the kind that
[439 Mass. 765] G.L. c. 149, ss
44A‑44H, were intended to regulate, and that Siemens's position was akin
to that of a material supplier. Once
the division found Siemens's product not satisfactory in relation to the
revised automatic temperature control specifications, it was free to direct the
general contractor to substitute a product and a provider that would meet those
specifications.
We need not address at length the
likelihood of irreparable harm to Siemens if an injunction is denied. As the motion judge noted, the "public
interest overlay" in this situation is significant. In the absence of some showing of illegal or
arbitrary action, a determination by the division that the public interest is
better served by having a single integrated campus‑wide automation
temperature control system provided by Johnson Controls should not be second
guessed by a court. Siemens has not
overcome the substantial public interest that would be adversely affected if an
injunction were granted. The request
for a preliminary injunction was properly denied.
4. Conclusion. The order of
the Superior Court judge denying Siemens's request for a preliminary injunction
is affirmed and the case is remanded to the Superior Court for further
proceedings consistent with this opinion.
So
ordered.
(FN1.) Johnson Controls, Inc. (Johnson
Controls); N.B. Kenney Company,
Inc.; and Suffolk Construction Co.,
Inc.
(FN2.) The decision of the university to
change the campus‑wide automatic temperature control systems to those
manufactured by Johnson Controls was the result of recommendations made under
an energy conservation contract that the university had entered into separate
from the campus center construction contract at issue here.
(FN3.) The complaint alleges both breach of
contract and violation of the public bid statute. On appeal, however, Siemens makes no allegation of breach of
contract separate from its statutory claim.
(FN4.) With few exceptions, this procedure is
applicable to all public contracts for the "construction, reconstruction,
installation, demolition, maintenance or repair of any building" as long
as the public agency estimates the contract to exceed $25,000. G.L. c. 149, s 44A (2).
(FN5.) Because sub‑subcontractors are
listed in paragraph E of the subbid form, they are sometimes referred to as
"paragraph E firms."
(FN6.) Siemens quotes J.F. White Contr. Co. v.
Department of Pub. Works, 24 Mass.App.Ct. 932, 933, 508 N.E.2d 637 (1987),
for the proposition that "once a subbid is filed in accordance with the
bid documents, it may not be changed."
In that case, however, the contracting agency extended the completion
date of a project after it had accepted the subbids and then refused to pay the
resulting higher labor costs of the subcontractor. A subcontractor's protection against an agency's modification of
the terms of the subcontract has nothing to do with an agency's power to
replace an unsatisfactory sub‑subcontractor.
(FN7.) That the division's letter informing
Siemens of its decision to replace it in "the best interests of the
Commonwealth" did not state that its system was not satisfactory is not
determinative. No magic words were
required to find its product not satisfactory under G.L. c. 149, s 44F (2),
par. F, and Siemens fully understood
that its system was not approved.
(FN8.) Siemens relies on G.L. c. 30, s 39M (b ), to argue that the division was
required to make a written statement of its reasons for awarding the automatic
temperature control work to Johnson Controls rather than opening the work up
for public bid. Section 39M (b ) establishes that if an agency places
specifications in a project that will limit full competition for that contract,
the agency must provide "sound reasons in the public interest" upon
written request. However, the section
applies to specifications for contracts awarded and not to the bidding and
awarding of sub‑subcontracts.
(FN9.) There is also no provision in G.L. c.
149 that would require the division in such a situation to rebid the entire
heating, ventilating, and air conditioning subcontract.