Court: APPEALS COURT OF MASSACHUSETTS
Citation: 7 Mass. App. Ct. 913
Parties: POWERS REGULATOR COMPANY vs. UNITED STATES FIDELITY &
GUARANTY COMPANY & another. (Rescript Opinions.)
Decision Date: May 3, 1979
1. The judge did not err in ruling that the plaintiff, a supplier of materials
to the defendant subcontractor Brandt-Jordan Corp., could recover from the
defendant surety company on the payment bond given by the subcontractor to the
general contractor. That bond was conditioned on the subcontractor's making
"payment to all persons supplying to [it] labor and material in the
prosecution of the work provided for in [the] contract and [on the
subcontractor's] sav[ing] harmless the [general contractor] against any
expenditure or loss . . . arising from claims against the [general contractor]
. . . by those claiming to have supplied labor and materials to [the
subcontractor] . . . in connection with the said work" (emphasis
supplied). By the express terms of G. L. c. 149, Section 29A, the plaintiff, as
a supplier of materials to whom payment was due, could bring an action on the
bond directly against the surety. "The purpose of Section 29A was to
create a statutory exception to the rule of law in this Commonwealth which had
been held to preclude recovery under a contract by a third-party
beneficiary." M. Lasden, Inc. v. Decker Elec. Corp., 372 Mass. 179, 182
(1977). The statute "should be broadly construed to effectuate its
self-evident policies." Id. at 183. It is not a requirement of Section 29A
that a supplier be named in the bond as an obligee in order to sue thereon; nor
does the statute distinguish between a bond given by a general contractor to
the owner and one given by a subcontractor to the general contractor. Compare
17 Am. Jur. 2d Contractors' Bonds Sections 15 and 16 (1964). Cases reaching the
same result in the absence of such a statute include Pacific States Elec. Co.
v. United States Fid. & Guar. Co., 109 Cal. App. 691, 694 (1930); Pacific
Natl. Fire Ins. Co. v. Cummins Diesel of Georgia, Inc., 213 Ga. 4, 7 (1957);
Fidelity & Deposit Co. v. Pittman, 52 Ga. App. 394, 398-399 (1936);
Griffith v. Stucker, 91 Kan. 47, 52-53 (1913); Parliament Ins. Co. v. L.B.
Foster Co., 533 S.W.2d 43, 50 (Tex. Ct. Civ. App. 1975). See also cases
collected at 118 A.L.R. 90 (1939). 2. The judge did not err in adopting that
portion of the master's report wherein the master found the subcontractor
liable to the plaintiff for extra work in accordance with the finding of an
arbitrator. Arbitration of "any disputes arising out of or relating to
this subcontract" was expressly provided for in the subcontract, which, in
turn, was incorporated by reference in the
Page 914
payment bond. As the surety company agreed implicitly to that method of
determining the contractual liability of its principal (the subcontractor), it
could avoid the result of the arbitration only by showing that it was obtained
by fraud or collusion. See Giatas v. Demoulos, 271 Mass. 51, 53-54 (1930);
Martiniello v. Robitaille, 293 Mass. 200, 202-203 (1936). No such contention
was made.
Judgment affirmed.
END OF DECISION