Court: APPEALS COURT OF MASSACHUSETTS
Citation: 59 Mass. App. Ct. 816 (2003)
Parties: OSTROW ELECTRICAL CO. v. J.L. MARSHALL
& SONS, INC., St. Paul Fire and Marine Insurance Company and Michael D.
Waters., City Of Worcester, third‑party defendant; Perry Dean Rogers & Partners: Architects, fourth‑party defendant.
Docket
No.: 01-P-1487
Decision Date: NOVEMBER 5, 2003
Judges: DOERFER, J.
Sally
A. Corwin (Carolyn M. Francisco with her), Boston, for the plaintiff.
Jeffrey
L. Alitz, Boston, for Michael D. Waters & another.
James
F. Grosso, Southboro, for J.L. Marshall & Sons, Inc.
Donald
V. Rider, Jr., Assistant City Solicitor, for city of Worcester.
Present: DOERFER, McHUGH, & KAFKER, JJ.
Electrical subcontractor on public
works project brought statutory action for unfair trade practices against
general contractor, its surety, and project architect, general contractor
brought third‑party claim for indemnification against city, and city
brought fourth‑party claim for indemnification against architectural
firm. The Superior Court Department,
Suffolk County, Herman J. Smith, Jr., J., granted summary judgment for
architect, and denied summary judgment on city's third‑party claim, and
the same court, Judith Fabricant, J., entered judgment on damages, costs, and
fees. Appeal was taken. The Appeals Court, Doerfer, J., held that:
(1) architect did not act arbitrarily and capriciously in interpreting contract
documents, and (2) architect did not act in bad faith.
Decision by architect on public
works project, that audiovisual subcontractor, not electrical subcontractor,
was required to supply speakers and backboxes, was not arbitrary and
capricious; under contract,
specifications requiring that audiovisual subcontractor supply these items took
precedence over drawing assigning this duty to electrical subcontractor.
Architect on public works project
did not act in bad faith by interpreting contract to provide that audiovisual
subcontractor, not electrical subcontractor, had duty to supply speakers and
backboxes; there was a severe ambiguity
in contract, and architect discussed the matter with construction manager,
drafters of specifications, and another architect. M.G.L.A. c. 93A, s 11.
The Worcester Convention Center is
equipped with an elaborate audiovisual system that includes numerous loudspeakers. Associated with most of these loudspeakers *311
is a "backbox" that houses the loudspeaker and into which
wires run. A controversy developed
during construction between Ostrow Electrical Co. (Ostrow), the audiovisual
subcontractor, and Coughlin Electric Company, Inc. (Coughlin), the electrical
subcontractor, about who was responsible for supplying and installing these
backboxes. Coughlin is not a party to
this litigation. Pursuant to the
relevant terms of the general construction contract and subcontracts, the
dispute was submitted to the architect, Perry Dean Rogers & Partners: Architects (Perry Dean). Michael D. Waters (Waters) is the architect
employed by Perry Dean who took on the task of resolving the dispute. Waters determined that the responsibility
belonged to Ostrow. Ostrow did the work
under protest and brought a claim against Waters under G.L. c. 93A, s 11,
alleging that Waters had acted in bad faith.
Ostrow also sought to recover the cost of this work as a back charge
against the general contractor, J.L. Marshall & Sons, Inc. (Marshall), and
St. Paul Fire and Marine Insurance Company, the surety for Marshall. Marshall brought a third‑party
complaint seeking indemnification from the city of Worcester (city); the city in turn brought a fourth‑party
complaint seeking indemnification from Perry Dean. (FN2)
A judge of the Superior Court
granted Waters's motion for summary judgment on the G.L. c. 93A, s 11, claim
and Ostrow's motion for summary judgment against Marshall and its surety on the
back charge. The judge also denied
Marshall's motion for summary judgment on its third‑party complaint
against the city for indemnification.
(FN3) A second judge entered
judgment on those claims and determined the damages, costs, and fees owed
Ostrow by Marshall. All rulings are
before us on appeal or cross appeal by the parties adversely affected thereby.
[59
Mass.App.Ct. 818] 1. Background. As is usual in large public contracts, the work to be done by
various subcontractors was specified in numbered sections of the
specifications. Subcontractors were
invited to file bids on the work to be done.
These filed subbids were reviewed and the subcontracts awarded based
upon an evaluation of each subbid by the awarding authority.
Each subcontractor was issued a set
of the documents relevant to its bid, including drawings, specifications, and
addenda. Prior to and during the
bidding process, the original documents were subject to addenda, and each
subcontractor was responsible for reviewing all addenda to make sure it knew
what it was bidding on.
Section 17100 of the specifications
dealt with the work to be done by the audiovisual contractor, Ostrow. Under "General Requirements,"
paragraph E states:
"Provide materials, labor, equipment and
services necessary to furnish, deliver and install all work of this section as
shown on the drawings, as specified herein and/or required by job
conditions."
Paragraph F states:
"The work shall include, but is not limited
to, the supply and installation audiovisual [sic ] systems as specified herein and shown on drawings."
Section 2.05 "Specific Detail
Capabilities," provides, inter alia:
"K. Loudspeaker Systems
*312 3.
Schedule of Loudspeaker Types by Area
S1. 12" Ceiling Speaker with co‑axial
horn and compression driver.... Complete with backbox, baffle/grille.
S2. 6.5" Ceiling Speaker....
Complete with backbox, baffle/grille.
S3. 4" Ceiling speaker....
Complete with backbox, baffle/grille."
(Emphasis
supplied.) Also listed under par. K.3 was another [59 Mass.App.Ct. 819]
weatherproof speaker, S4, for use at the loading docks and entrance canopy,
which did not utilize a backbox.
Section 17100 also contained the following paragraph:
"1.01 Work Specified Elsewhere.
A. All
conduits, wireways, connection boxes, pull boxes, junction boxes, andoutlet boxes permanently installed in walls,
floors, and ceilings, provided under applicable electrical sections "
(emphasis supplied).
Section
16000 of the specifications dealt with the work to be done by the electrical
subcontractor, Coughlin. The electrical
drawing, E15, contained a note stating that "the electrical contractor
shall provide ... [the] speaker backboxes." The word "provide" was defined in section 4.4.1 of the
general conditions of the contract as meaning "furnish and install
complete ... unless otherwise specified." As amended by addendum 7, (FN4) section 16000 also gave
responsibility to the electrical subcontractor for "outlet boxes" by
cross‑referencing section 1.01, "Work Specified Elsewhere," in
section 17100, the audiovisual specifications.
Thus,
a conflict existed between the requirement in the audiovisual specification
that Ostrow supply and install the listed speaker, type S1, S2, and S3,
complete with backboxes, and the statement in drawing E15 that the electrical
subcontractor was to provide the backboxes.
Also unclear was the import of the assignment of "outlet
boxes" to the electrical contractor, as set forth in addendum 7, while the
audiovisual specifications assigned speaker "backboxes" to the
audiovisual subcontractor.
The
contract provided for the resolution of disputes of this kind as follows:
"2.2.7 The Architect will be the
interpreter of the requirements[59
Mass.App.Ct. 820] of the Contract Documents and the judge of
the performance thereunder by both the Owner and Contractor.
"2.2.8
The Architect will render interpretations necessary for the proper execution or
progress of the work, with reasonable promptness and in accordance with M.G.L.
c. 30, section 39P, or any lesser time limit agreed upon. Either party to the Contract may make
written request to the Architect for such interpretations.
"2.2.9
Claims, disputes and other matters in question between the Contractor and the
Owner [or subcontractor and contractor] relating to the execution of [sic ] progress of the Work or the
interpretation of the Contract Documents shall be referred initially to the
Architect for decision which he will render in writing within a reasonable
time.
*313 "2.2.10 All interpretations and
decisions of the Architect shall be consistent with the intent of and
reasonably inferable from the Contract Documents and will be in writing or in
the form of drawings. In his capacity
of interpreter and judge he will endeavor to secure faithful performance by
both the Owner and the Contractor, will not show partiality to either, and will
not be liable for the result of any interpretation or decision rendered in good
faith, and in the absence of negligence, in such capacity."
[1] 2. Discussion. (a) Error in
resolving the dispute. As noted
above, the dispute was submitted to Waters for resolution. General Laws c. 30, s 39J, as inserted by
St.1961, c. 538, s 1, prevents a decision made by an architect from being
"final" or "conclusive" "if such decision is made ...
capriciously, or arbitrarily[,] is unsupported by substantial evidence, or is
based upon error of law." (FN5) Ostrow argues that Waters's decision had [59 Mass.App.Ct. 821] no rational basis and thus was
arbitrary and capricious and constitutes an error of law.
Waters took the position in
resolving this controversy that specification 17100 for audiovisual work
explicitly required Ostrow to furnish "backboxes" and that the
references to "outlet boxes" in addendum 7 to the electrical
specifications did not shift the backbox work from Ostrow to the electrical
subcontractor. As for the direct
references in electrical drawing E15 to backboxes, Waters took the position
that such references were superceded by the language in the
specifications. He relied on the order
of priority of documents as specified in the contract: Section 1.1.1 of the General Conditions
states:
"In the event of any conflict among the
Contract Documents, the Documents shall be construed according to the following
priorities: Highest Priority‑‑Modifications,
Second Priority‑‑Agreement, Third Priority‑‑Addenda‑later
date to take precedence, Fourth Priority‑‑Special Requirements,
Fifth Priority‑‑Special Conditions, Sixth Priority‑‑Supplementary
General Conditions, Seventh Priority‑‑General Conditions, Eighth
Priority‑‑Specifications, Ninth Priority‑‑Drawings."
Waters reasoned that Ostrow's duties
to provide backboxes was provided for in the specifications, whereas the
electrical subcontractor's duties to provide the backboxes were specified only
in the drawings. Since specifications
take precedence over drawings, Waters determined that the obligation for
backboxes fell to Ostrow.
Ostrow argues that the language in
the drawings was put there in connection with addenda 4 and 7, and addenda take
precedence over specifications. As to
addendum 4, (FN6) Waters argues that it merely reduced *314 the number of
drawings that the [59 Mass.App.Ct.
822] electrical subcontractor needed
to look at to find out what its work was.
Addendum 4 did not address what the work of the audiovisual
subcontractor was supposed to be. Waters
argues that, by issuing an addendum that referred to a drawing relating to electrical
work, the relative priority of those drawings was not increased to trump a
provision of the audiovisual specification telling the audiovisual
subcontractor what work was required of it.
We cannot say that Waters's determination was incorrect as matter of law
or that it was arbitrary and capricious.
His decision is therefore final.
See G.L. c. 30, s 39J.
As to the terms of addendum 7,
Ostrow submitted an affidavit referencing addendum 7's exclusion of
"outlet boxes" from work to be done by the audiovisual subcontractor,
and averred, "I knew from my experience and the Mass. Electric Code that
[the] term ["outlet boxes"] includes speaker backboxes." The "General Conditions" of the
contract provide, "Words and abbreviations which have well‑known
technical or trade meanings are used in the Contract Documents in accordance
with such recognized meanings."
Ostrow, however, did not submit a copy of the electric code.
Waters concluded that, because
addendum 7 did not specifically exclude speaker backboxes, there was no
conflict between the requirement in section 17100 that the audiovisual
subcontractor provide speaker backboxes, and the addendum's assignment of
outlet boxes to the electrical subcontractor.
Waters disputes the contention that the specific term
"backboxes" is equivalent to the generic term "outlet
boxes." While Waters does not
dispute that outlet boxes can "include" speaker backboxes, as Ostrow
averred (speaker backboxes being a particular type of outlet box), Waters
argues that, since the audiovisual specification explicitly includes in
Ostrow's responsibility the provision of speaker backboxes while at the same
time specifically excluding from Ostrow's work the responsibility to provide
"outlet boxes," the two terms cannot mean the same thing. We conclude that Waters's decision was
plausible and cannot be characterized as having no rational basis. The decision, therefore, was not arbitrary
and capricious, and there was no error of law.
[2] [59 Mass.App.Ct. 823]
Neither did the architect, as Ostrow argues, make a new contract by
interpreting the ambiguities in the contract.
"Contract terms are not changed when the architect decides in the
course of a job what a specification means or whether one specification trumps
another." Fontaine Bros. v. Springfield, 35 Mass.App.Ct. 155, 159, 617
N.E.2d 1002 (1993). Compare Perini Corp. v. Massachusetts Port Authy.,
2 Mass.App.Ct. 34, 42‑44, 308 N.E.2d 562 (1974); Acmat Corp. v. Daniel
O'Connell's Sons, 17 Mass.App.Ct. 44, 49, 455 N.E.2d 652 (1983). Contrast
J.A. Sullivan Corp. v. Commonwealth, 397 Mass. 789, 800, 494 N.E.2d 374
(1986) (where the contract did not state that the architect's decision was
final as between the parties, the judge could decide issues of contract
interpretation at trial).
[3] (b) Bad faith claim against the architect. Ostrow's claim for summary judgment under G.L. c. 93A, s 11, is
based on an argument that, on these facts, Waters acted in bad faith as a
matter of law. Waters's cross motion
for summary judgment reasons that the facts show that he at least made a
reasonable judgment as to the relative obligations of the electrical and
audiovisual subcontractors which cannot
*315. form the basis of liability
under G.L. c. 93A, s 11. Ostrow's
arguments are overdrawn and were properly rejected by the motion judge. The foregoing discussion shows that there
was a severe ambiguity, one might say contradiction, in the contract documents
as to who was responsible for the speaker backboxes. (FN7) Waters's resolution
of that conflict cannot, as a matter of law, support an inference of bad
faith. Compare Kobayashi v. Orion Ventures, Inc., 42 Mass.App.Ct. 492, 505, 678
N.E.2d 180 (1997). Contrast Nota Constr. Corp. v. Keyes Assocs., 45
Mass.App.Ct. 15, 21‑22, 694 N.E.2d 401 (1998).
Other evidence in the summary
judgment record shows that Waters consulted others in an attempt to resolve the
issue rationally. In addition to
reviewing the contract documents, the [59
Mass.App.Ct. 824] record shows that
Waters discussed this matter with Gilbane, the construction manager, the
drafters of the specifications, and another architect at Perry Dean.
The motion judge did not err in
denying Ostrow's motion and allowing Waters's motion for summary judgment on
Ostrow's c. 93A claim.
Conclusion.
Because we conclude that Waters did not err in construing the contract, the
judgment for Ostrow on its claim against Marshall and St. Paul Fire and Marine
Insurance Company cannot stand, and Marshall's third‑party complaint against
the city of Worcester is therefore moot.
Accordingly, the judgment is affirmed as to the c. 93A claim and the
dismissal of Marshall's third‑party complaint against the city of
Worcester. The judgment is reversed as
to the award to Ostrow on its claim against Marshall and St. Paul Fire and
Marine Insurance Company.
So
ordered.
(FN1.) St. Paul Fire and Marine Insurance
Company and Michael D. Waters.
(FN2.) Ostrow also brought a cross claim
against Perry Dean for any sums Waters was unable to pay.
(FN3.) The city's fourth‑party
complaint against Perry Dean was dismissed without prejudice as the third‑party
complaint had been dismissed on the merits.
(FN4.) Addendum 7 was an addendum to the
electrical specifications. It added a
paragraph 19 to page 16000‑3, par. 1.02 A., providing, "Audiovisual
Systems per 17000‑2 1.01 A & B." See "1.01 Work Specified
Elsewhere,"supra. Thus, section 1.01 A added to the
electrical subcontract what had been excluded from the audiovisual contract.
Section B referred to "electrical breaker
panels" required to power audiovisual systems.
(FN5.) There is no merit to Waters's argument
that the parties expressly agreed in the contract that the decision of the
architect on such matters was binding so long as the architect acted in good
faith. This is, in effect, an argument
that G.L. c. 30, s 39J, does not operate where, as here, there is an express
clause giving the architect authority to resolve disputes which does not
contain the limitation relating to errors of law found in the statute. However, the statute itself specifically
provides, "[n]otwithstanding any contrary provision of any contract,"
and thus the terms of the contract cannot undermine the requirements of the
statute.
(FN6.) Addendum 4 changed par. E in "Part 1‑General 1.00 Filed
Sub‑Bid Requirements" of the electrical specification from
"Work in this Section is shown on all drawings (general, civil, landscape,
architectural, structural, fire protection, plumbing, HVAC/mechanical, electrical)
shown on Cover Sheet" to "Work in this section is shown on
Electrical, Audio Visual and Food Service drawings as listed on sheet G 1 of
the drawings. All other drawings; Civil, Architectural, Structural, Fire
Protection, Plumbing and HVAC/Mechanical are to be referenced for information
and coordination with regards to installation of all electrical work."
(FN7.) Indeed, the problem of which
subcontractor was required by the contract to furnish the backboxes seems
severe enough to have alerted the parties to resolve it before submitting a
bid. All of the ambiguities that gave
rise to this litigation were readily apparent in the documents upon which the
subcontractors submitted their bids. As
provided for in section 3 of the instructions to bidders, any subcontractor had
the right to submit questions and receive clarifications of questions raised by
the plans, specifications, and other contract documents before submitting a
bid. Compare Fontaine Bros. v. Springfield, 35 Mass.App.Ct. at 157, 617 N.E.2d
1002.