Court: APPEALS COURT OF MASSACHUSETTS
Citation: 1 Mass. App. Ct. 213
Parties: METRO INSULATION CORP. vs. ROBERT LEVENTHAL &
others.
County: Suffolk
Hearing Date: February 13, 1973
Decision Date: April 12, 1973
Judges: HALE, C.J., GOODMAN, & GRANT, JJ.
In a suit in equity under G. L. c. 149, Section 29, by a sub subcontractor doing insulation work on a construction project for a municipal housing authority, where it appeared that the plaintiff, at a conference with the general contractor, the plumbing subcontractor, the authority's architect, the engineer employed by the architect, and the authority, was "informed by all those present that a change order
Page 214
for . . . proposed extra insulation work in the amount of . . . [the
plaintiff's] proposal was forthcoming and that . . . [the plaintiff] was to
proceed with the work immediately," that the plaintiff then went ahead
with the work "in reliance on . . . authorization[s] to proceed and . . .
agreement to pay it additional money," and that it completed the work
before receiving notice that the Department of Housing and Urban Development
refused to approve the change order, it was held that there was no
"dispute" between the general contractor and the authority within an
article in the basic contract calling for presentment to the architect for
decision of "all disputes . . . arising under this Contract . . .
involving . . . extra work," and that the plaintiff was entitled to
payment for the work done as an extra. [214-218] Where a contractor seeking to
recover under G. L. c. 149, Section 29, extra payments for insulation of
sprinkler piping in a municipal housing project asserted in its affidavit in
support of a motion for summary final decree under c. 231, Section 59, that
"it is not the custom . . . to insulate sprinkler piping," and the
defendants did not take issue with that assertion in their counter affidavit,
the judge properly allowed the motion, and the defendants were precluded from
raising the question of custom for the first time in this court. [219] In a
suit in equity under G. L. c. 149, Section 29, where the final decree correctly
ordered the general contractor on a project of a municipal housing authority
and the surety on the contractor's bond to pay the plaintiff sub subcontractor
for certain extra work, this court ordered the final decree modified by adding
thereto a provision that upon such payment the authority reimburse the payer.
[219-220]
BILL IN EQUITY filed in the Superior Court on August 14, 1968.
The suit was heard by Good, J.
Robert J. Sherer (Judith K. Wyman with him) for Robert Leventhal & others.
Peter J. Gagne (Sally A. Corwin with him) for Metro
Insulation Corp.
Brian P. Shillue for Boston Housing Authority.
GRANT, J. This proceeding under G. L. c. 149, Section 29 (as amended through
St. 1964, c. 609, Sections 4 and 5), was originally brought by Metro Insulation
Corp. (Metro), a sub subcontractor, against persons doing business as Beacon
Construction Company1 (Beacon), the
general contractor,
-------------------------
1 Robert Leventhal and Norman B.
Leventhal.
Page 215
and the surety on Beacon's bond2 to
recover for two extras of insulation work performed by Metro3 in connection with the construction of a federally
assisted housing project for the elderly owned by the Boston Housing Authority
(Authority). The Authority was brought into the proceeding on Beacon's
counterclaim alleging, in effect, that the Authority should be responsible to
Beacon for any liability for extras which Metro might succeed in establishing.
Frank Sullivan Co. (Sullivan), the plumbing subcontractor and the concern with
which Metro had its direct contractual relationships, was not joined as a
party.
Metro, following Beacon's responses to Metro's notices to admit facts, moved
with supporting affidavit for the entry of a decree in its favor (G. L. c. 149,
Section 29; G. L. c. 231, Section 59). Beacon filed an affidavit in opposition
to Metro's motion and (together with the surety) moved, with supporting
affidavit, for dismissal of Metro's original bill or, in the alternative, for a
decree against the Authority. The Authority filed an affidavit in opposition to
so much of Beacon's motion as was directed to it, but no affidavit directly
responsive to the matters set out in Metro's affidavit. After hearing the
Superior Court allowed Metro's motion, denied Beacon's motion, and entered a
final decree ordering Beacon and its surety to pay Metro the total of both
extras (see fn. 3, supra). Beacon and the surety have appealed from the
interlocutory decree denying their motion and from the final decree.
We shall confine our consideration of the case to the specific issues which
have been argued in the briefs of the parties. Rule 1:13 of the Supreme
Judicial Court, 351 Mass. 738. Rule 1:13 of the Appeals Court. Beacon does not
seriously dispute Metro's right to recover for either of the claimed extras,
contending instead that the ultimate responsibility should lie with the
Authority to pay for all work
-------------------------
2 Great American Insurance Company.
3 A claim for a contract balance due
Metro has been eliminated from the case by stipulation of the parties filed in
the Superior Court after the entry of the final decree appealed from.
Page 216
not required under the basic contract between itself and the Authority. The
Authority's main reliance is on the asserted failure of Metro and Beacon to
comply with procedural requirements found in the basic contract. As the two
claims for extras are unrelated we discuss them separately. The facts recited
are taken from Beacon's responses to Metro's notices to admit and from the
various affidavits. None of them is disputed.
1. The first claim for extra payment is with respect to Metro's insulation of
certain hot water piping in the seventh floor ceiling and of certain cold water
piping in the pump and boiler rooms of the building.
At some point in time prior to June 13, 1967, the engineer employed by the
Authority's architect inquired of Metro as to the type of insulation it
proposed to employ in the upper floors of the building. By its letter of that
date to the engineer Metro replied that the specifications of the basic
contract did not call for the insulation of such piping4 and that it had not carried anything for such insulation
in the bid which it had submitted to Sullivan, the plumbing subcontractor. By
letter of June 30 Sullivan requested Metro to submit a price "for the hot
water piping not covered by the specifications." By letter of July 17
Metro submitted separate prices to Sullivan for insulation of hot water piping
in the seventh floor ceiling and cold water piping in the pump and boiler
rooms. Acting on a request from the Authority, Sullivan instructed Metro to
send a breakdown of its quotations "priced in accordance with the contract
specifications." Metro did so, and Sullivan in turn sent the revised
quotations to Beacon on August 21. On August 22 Beacon wrote Sullivan that the
architect had "verbally authorized that this insulation was to be
installed and that it was subject to a change order" and concluded by
saying that "[i]n the meantime, it appears
-------------------------
4 Division 28.21 o of the specifications
("Pipe Covering and Insulation"), as amended by Addendum No. 3,
called for: "(1) All hot water supply and return piping, branches, risers,
and also including cold water piping throughout the first floor ceiling shall
be insulated with . . .. (3) Insulate all water lines in first floor ceiling
with . . ." (emphasis supplied).
Page 217
that we are authorized to proceed with this change." Sullivan, by a letter
of August 24, sent a copy of Beacon's letter to Metro.
Following Metro's receipt of the last two letters a conference was had between
and among Metro, Sullivan, Beacon, the architect, the engineer and the
Authority at which Metro was "informed by all those present that a change
order for the proposed extra insulation work in the amount of Metro's proposal
was forthcoming and that Metro was to proceed with the work immediately so as
not to hold up" the project. Metro thereafter went ahead and completed the
work "in reliance on the oral and written authorization to proceed and the
agreement to pay it additional money."5 The Authority, apparently acting under the provisions of
art. 10 of the General Conditions of the basic contract,6 submitted a relevant change order to the Department of
Housing and Urban Development (HUD) for its written approval. HUD, for reasons
we need not assess, refused to approve the change order for the insulation
work. Metro does not appear to have received notice of such disapproval until
on or about November 14, 1967, by which time it had completed the work for
which it now seeks to recover the price quoted by it. There then followed a
flurry of correspondence whereby those concerned either did or did not succeed
in complying with the requirements of art. 157 of
-------------------------
5 Although no separate document
identifiable as a change order has been made part of the record, it may be
inferred from several documents which are in the record that a change order was
in fact issued and approved by representatives of the Authority, the architect
and the engineer.
6 That article, entitled "Changes in
the Work," provides in pertinent part as follows: "a. The Authority
may make changes in the work of the Contractor by making alterations therein,
or by making additions thereto, or by omitting work therefrom, without
invalidating the Contract . . . . c. Except in an emergency endangering life or
property, no change shall be made by the Contractor unless he has received a
prior written order from the Authority, countersigned by the Architect, and
approved on its face by the . . . [Department of Housing and Urban Development]
authorizing the change, and no claim for an adjustment of the Contract price or
time shall be valid unless so ordered."
7 That article, entitled
"Disputes," provides in pertinent part as follows: "a. All
disputes . . . arising under this Contract or its interpretations, whether
involving law or fact, or both, or extra work, . . . shall within 10 days of
commencement of dispute be presented to the Architect for decision. A copy of
the notice of the dispute shall be sent to the Authority and the Regional
Office of . . . [HUD]. Such notice need not detail the amount of the claim but
shall state the facts surrounding the claim in sufficient detail to identify
the claim, together with its character and scope. In the meantime the
Contractor shall proceed with the work as directed. The parties agree that any
claim not presented within this subsection is waived . . .. b. The Contractor
shall submit in detail his claim and his proof thereof. The decision of the
Architect shall be approved in writing by . . . [HUD] and the Authority prior
to its issuance. Any decision not so approved shall be a nullity. . . . d. . .
. The Architect's decision shall not be final and conclusive but the dispute
shall be tried in court on its merits. . . ."
Page 218
the General Conditions of the basic contract. We need not decide any question
in that regard.
No one contends that the insulation work which forms the basis of this claim
was required by the specifications. Beacon suggests, and the Authority argues,
that the claim should be barred by the failure of Metro and Sullivan to comply
with the notice and other requirements of art. 15 of the General Conditions
(fn. 7) following HUD's failure to approve the change order.8 We do not think there was a "dispute" within
the meaning of art. 15; almost as soon as the problem was discovered, and even
before HUD approval was sought, it was expressly agreed by the architect and
all the parties to this litigation that the insulation requested by the
architect was not required by the specifications and should be paid for as an
extra.9 Cf. Chiappisi v. Granger
Contracting Co. Inc. 352 Mass. 174, 176-178; Beacon Construction Co. of
Massachusetts v. United States, 314 F. 2d 501, 504 (Ct. Cl.). If the Authority
had requested us to consider the effect of the provisions of art. 10 of the
General Conditions (fn. 6), we would have regarded them as waived by the
Authority's actions, prior to seeking HUD approval of the change order, in
directing the work to proceed and agreeing that it should be paid for. See
Stuart v. Cambridge, 125 Mass. 102, 109-110; Farm-Rite Implement Co. v.
Fenestra Inc. 340 Mass. 276, 286-287;
-------------------------
8 Metro agreed with Sullivan to
"[f]urnish & install the necessary insulation as per the requirements
of the Contract Plans & Specification . . .." For purposes of this
opinion we assume without deciding that Metro agreed to be bound by the General
Conditions of the basic contract. See, on this point, John Soley & Sons,
Inc. v. Jones, 208 Mass. 561, 566-567; Farm-Rite Implement Co. v. Fenestra Inc.
340 Mass. 276, 281, 283; S. C. 342 Mass. 427, 428-431, 434; Chiappisi v.
Granger Contracting Co. Inc. 352 Mass. 174, 175.
9 The Authority does not argue that it
cannot be held liable for an extra unless HUD participates therein. See Alpert
v. Commonwealth, 357 Mass. 306, 331-332.
Page 219
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc. 348 Mass. 682,
685-686; J. P. Smith Co. Inc. v. Wexler Construction Co. Inc. 353 Mass. 551,
554-555; Ferber Co. v. Ondrick, 310 F. 2d 462, 465 (1st Cir.); Wexler
Construction Co. Inc. v. Housing Authority of Norwich, 144 Conn. 187, 192-193.
2. The second claim for extra payment is with respect to Metro's insulation of
certain sprinkler piping in the first floor ceiling of the building. The
Authority's objection to payment of this claim is that the work in question was
already required under Division 28.21 o of the specifications (fn. 4)10 in the basic contract between itself and
Beacon. The specifications, read by themselves, are silent on the point. Metro,
apparently in anticipation of the Authority's objection, asserted (in the
affidavit filed in support of its motion for a decree) that "[i]t is not
the custom in the insulation trade to insulate sprinkler piping unless that
insulation is clearly specified" (see Fred C. McClean Heating Supplies,
Inc. v. Jefferson Construction Co. 339 Mass. 356, 369) and pointed in
particular to a contract drawing which clearly distinguished between the water
piping and the sprinkler piping to be installed in the first floor ceiling. A
copy of Metro's affidavit was attached to Beacon's motion (in the alternative)
for a decree against the Authority. Nothing in the Authority's affidavit took
issue with the factual assertions in Metro's affidavit concerning a custom in
the insulation trade. That being so, the Authority is in no position to urge
before us, for the first time, that it was entitled to a trial on the merits in
order to determine if any custom existed. Doral Country Club, Inc. v. O'Connor,
355 Mass. 27, 30. There was no error in summarily deciding that possible
question.
3. The Authority is ultimately responsible for payment of both of Metro's
claims for extras. The final decree (as already modified by stipulation) is to
be further modified by including therein a provision to the effect that the
-------------------------
10 Or, possibly, under Division 28.40
("SPRINKLER SYSTEM").
Page 220
Authority shall reimburse Beacon (or its surety) upon its payment of those
claims to Metro and, as so modified, is affirmed. Metro and Beacon are to have
costs of appeal against the Authority.
So ordered.
END OF DECISION