Court: APPEALS COURT OF MASSACHUSETTS
Citation: 28 Mass. App. Ct. 707
Parties: EMPIRE MASONRY CORP. vs. TOWN OF FRANKLIN & another.1
Docket No.: No. 89-P-1331.
County: Suffolk
Hearing Date: February 15, 1990
Decision Date: June 22, 1990
Judges: ARMSTRONG, KASS, & JACOBS, JJ.
A general contractor and a public authority awarding it a construction
contract under G. L. c. 149, Sections 44A-44H, are bound to apply the subbid
substitution procedures prescribed in G. L. c. 149, Section 44F (4) (c),
notwithstanding the fact that the low subbidder withdraws its subbid after
execution of the general contract; moreover, the general contractor is not
required by Section 44F (4) (c) to obtain executed subcontracts (with the
subbidders the contractor intends to use) prior to the execution of the general
contract. [709-716]
CIVIL ACTION commenced in the Superior Court Department on September 26,
1989.
A motion for preliminary injunctive relief was heard by Barbara A. Dortch, J.
A petition filed in the Appeals Court on October 20, 1989, was considered by
Brown, J., and questions of law were reported by him.
Peter J. Gagne for the plaintiff.
George M. Matthews for the town of Franklin.
KASS, J. Upon report by a single justice of this court we are to consider two questions: (1) whether in connection with public construction under G. L. c. 149, Sections 44A-44H, an awarding authority is bound by the substitution procedure described in G. L. c. 149, Section 44F(4)(c), if a low sub-bidder withdraws its sub-bid after execution of the general contract;
-------------------------
1 John T. Callahan & Sons,
Inc.
Page 708
and (2) whether, under Section 44F(4)(c), a general contractor must obtain
executed subcontracts for the subtrades on a job prior to execution of the
general contract. When the low filed sub-bidder falls away, the substitution
procedure requires the general contractor to look to the next lowest eligible
sub-bidder in the trade concerned, and so on up the line until a sub-bidder in
that trade signs up. In this case the town of Franklin ("the town")
is the awarding authority, John T. Callahan & Sons, Inc.
("Callahan"), is the general contractor, Rascicot Masonry
("Rascicot") is the sub-bidder who filed the lowest masonry sub-bid,
and Empire Masonry Corp. ("Empire") is the next lowest masonry
sub-bidder, who would be entitled to the masonry subcontract if the
substitution procedure is applicable.2
We add such details of the history of the controversy as are necessary to
consider the questions presented. Callahan was the low bidder with a bid of
$2,190,000 to build a police station for the town. Filed sub-bids were opened
June 26, 1989. Rascicot's low bid on the masonry component of the job was
$595,000.3 Empire was second lowest with
a bid of $661,000. The town conditionally awarded the general contract to
Callahan on July 20, 1989, subject to appropriation. In mid-August, the town
voted the appropriation for the work and on September 5, 1989, executed a
general contract with Callahan. The general contractor now called for signed
contracts from its designated sub-bidders.4 By letter dated September 7, 1989, Rascicot informed
Callahan that "[d]ue to financial circumstances we are unable to commence
this project . . . [and] must regretfully withdraw our bid. . . ."
Empire insisted that it was thereupon entitled to the masonry subcontract.
Callahan was entirely willing to have Empire do the work, provided that the
town adjusted the contract
-------------------------
2 Rascicot's sub-bid was restricted to
Callahan. Empire's sub-bid was unrestricted. Nothing turns on this.
3 As required by G. L. c. 149, Section
44B(2), Rascicot accompanied its sub-bid with a bid deposit of five percent of
its bid, $29,750.
4 The record is a bit obscure on
precisely when Callahan submitted contracts to its prospective subcontractors
but during argument counsel agreed that at least Rascicot received a contract
to sign on September 5.
Page 709
price to reflect Empire's higher price. The town took the position that it
had a contract for a fixed price with Callahan and it was Callahan's problem to
find a masonry subcontractor who would match Rascicot's price. On September 26,
1989, Empire brought an action for a declaratory judgment that it was entitled
to the subcontract as matter of right under the statutory scheme and for an
order restraining masonry work on the Franklin police station job by anybody
else. After a Superior Court judge denied injunctive relief, Empire sought
review before a single justice of this court under G. L. c. 231, Section 118. A
laudably pragmatic stopgap solution was arrived at. Empire was to proceed with
the masonry work. The town paid $66,000 (the amount by which Empire's bid
exceeded Rascicot's lowest bid) into an escrow account, pending decision of the
disputed questions, which the single justice referred to a full panel. If we
were to decide that the town was bound by the substitution procedure, the
escrow fund would be disbursed to Empire in proportion to so much of the
masonry work on the job as had been completed; were we to determine otherwise,
the escrow fund was to be disbursed to the town. Callahan would then bear the
incremental cost.
We conclude that the substitution procedure prescribed by Section 44F(4)(c) may
apply after execution of a general contract for a public construction job and
that it applied in this case.
To set the context we summarize how the public bidding system prescribed by G.
L. c. 149, Sections 44A-44H, works. All citations to statutory provisions are
to sections found in G. L. c. 149 (1988 ed.). The public agency undertaking the
construction project, the awarding authority, provides each general contractor
and subcontractor who so requests a set of plans and specifications for the
project. Section 44B(1). At least four days5 before the opening of general bids (Section 44F[3]),
sealed sub-bids must be filed with the awarding authority, accompanied by bid
deposits equal to five percent of the amount of the sub-bid. Sections 44B(2)
and 44F(3). Sub-bidders
-------------------------
5 Saturdays, Sundays and legal
holidays excluded. That qualification is added to every time limitation which
appears in the statutory scheme.
Page 710
may restrict use of their sub-bids to specified bidders on the general
contract (general bidders). Section 44F(2). The awarding authority is to open
the sub-bids forthwith. Section 44F(3).
Within two days, after weeding out all the formally defective bids, the
awarding authority sends out a list of the eligible sub-bidders (and their
sub-bids) to every person who had requested a set of plans and specifications.
Section 44F(3). General bidders must choose from among these listed sub-bidders
in preparing their bids, ibid., and, like the sub-bidders, they must include a
five percent bid deposit with their bid forms. Section 44B(2).
Within five days of the opening of the general bids, the awarding authority
rejects nonconforming bids (Section 44E[3]) and returns all the general bid
deposits, except those of the three lowest responsible and eligible general
bidders. Section 44B(3). Likewise, the bid deposits of all sub-bidders except
those of sub-bidders named by the three lowest responsible and eligible general
bids and those of the three lowest responsible and eligible sub-bidders for
each trade must be returned within five days of the opening of general bids.
Section 44B(4). If Federal approval of the contract is not involved, the
awarding authority is to award the general contract to the lowest eligible and
responsible general bidder within thirty days of the opening of the general
bids. Section 44A(3).
The selected general bidder then has five days in which to execute a contract
with the awarding authority in accordance with the general bid and to furnish
performance, labor and materials bonds in the sum of the contract price.
Section 44E(2). The bid deposits of the three lowest general bidders are
returned upon execution and delivery of the general contract. Section 44B(3).
If the selected general bidder fails to execute the contract and furnish the
bonds, the awarding authority keeps the bid deposit as liquidated damages
(Section 44B[3]) and awards the contract to the next lowest responsible and
eligible general bidder. Section 44A(3).
Once selected, the general bidder must "promptly" confer with the
awarding authority on the question of sub-bidders. Section 44E(2). The awarding
authority is entitled to replace any
Page 711
sub-bidder named in the general bid with a sub-bidder from the prepared
list, provided the selected general bidder does not object to that sub-bidder's
ability and standing. Ibid. There is no statutorily prescribed time within
which the selected general bidder must award subcontracts to sub-bidders. The
sub-bid form, however, requires that, within five days after presentation of
the subcontract by the selected general bidder, the selected sub-bidder must
execute a subcontract with the general bidder, "in accordance with the
terms of [the] sub-bid, and contingent upon the execution of the general
contract, and, if requested so to do in the general bid by the general
bidder," furnish a performance and payment bond for the full subcontract
price. Section 44F(2).
That brings us to the substitution procedure contained in Section 44F(4)(c)
which this case requires us to construe and apply. Section 44F(4)(c) provides
that, if the selected sub-bidder fails to execute the subcontract,
"contingent upon the execution of the general contract," and to post
the appropriate bonds, within five days after presentation of the subcontract,
the general bidder and the awarding authority must award the subcontract to the
next lowest responsible and eligible sub-bidder on the list to whose standing
and ability the contractor has no objection. The general contract price is
"adjusted," i.e., increased, by the difference between the second
lowest and the lowest sub-bid. The subcontractor who has declined to sign up
forfeits his or her bid deposit to the awarding authority. Section
44B(4).6
An illustration under this labyrinthine (and mind-numbing) statute may help to
demonstrate that substitution of a sub-bidder may occur before or after
execution of the general contract. Consider the following scenario. The general
contract
-------------------------
6 Section 44B(4) provides that the
awarding authority must return the sub-bid deposits still in its possession --
i.e., those of the three lowest sub-bidders and of the sub-bidders named by the
three lowest general bidders -- within five days of the execution of the
general contract. This means that sub-bid deposits will be available to the
awarding authority to soften the financial blow of substitution only for five
days after the execution of the general contract.
Page 712
is awarded on a day we establish as day one.7 One would expect that a general contract is presented to the selected general bidder on the same day as the award. Under Section 44E(2), the selected general bidder then has five days after presentation to execute the general contract, i.e., by day six. To continue with our illustration, after consulting with the awarding authority immediately after contract award on day one, the selected general bidder awards the masonry subcontract to sub-bidder A (the lowest masonry sub-bidder) on day two. Under Section 44F(2), sub-bidder A has until day seven to execute the masonry subcontract. Sub-bidder A fails to sign up before day seven. The subcontract, by operation of Section 44F(4)(c), is, therefore, awarded to sub-bidder B, the second lowest masonry sub-bidder, at B's price. The general contract price is increased by the amount B's price exceeds A's. Section 44F(4)(c). As the reader will notice, the selected bidder in the example acted very promptly after award of the general contract to sign up sub-bidder A. Nonetheless, the time allowed sub-bidder A to execute the subcontract -- five days after presentation -- is such that the substitution procedure will inevitably be triggered after execution of the general contract. In fact, the substitution procedure can be triggered before execution of the general contract only if the contractor executes a subcontract prior to being awarded the contract, or if the subcontractor bows out before the five days to sign the subcontract have expired.8
-------------------------
7 The award
of the contract should occur within thirty days of the bid opening. Section
44A(3). That period was exceeded in this case, but the general contractor seems
to have acquiesced in that, and no party complains of that particular
irregularity in the bidding process.
8 It is
possible under the statute for the general contract to be awarded on day one
and executed on day six, and for the general contractor not to award the
subcontract to sub-bidder A until two weeks later, on day twenty. In this case,
substitution could properly occur any time before day twenty-five, even though
all the sub-bid deposits would have been returned by day eleven. (The bid
deposits of the three lowest sub-bidders are to be returned within five days
after execution of the general contract. Thus, if the general contract is not
executed until day six, the date to return these bid deposits falls on day
eleven. See Section 44B[4].) A cautious awarding authority might protect itself
by requiring the selected general bidder to present subcontracts to sub-bidders
before execution of the general contract. Such a requirement would mean that if
sub-bidder A failed to sign a subcontract and furnish bonds within five days of
presentation, and sub-bidder B were consequently substituted at B's price, the
awarding authority would have the benefit of A's sub-bid deposit to offset the
increased contract price. If the selected subcontractor defaulted after
execution of the subcontract, the payment and performance bonds would act as a
safety net for the general contractor. While this course of action would be
prudent, it is not, as the town suggests, required by the statute.
Page 713
Apart from the forty-seven day gap between the selection of the general
contractor and execution of the general contract, the facts of the instant case
are parallel to those posited in the illustration. Callahan and the town
executed the general contract on September 5. By statute, the town could
rightfully retain Rascicot's sub-bid deposit until September 10. Callahan
presented the masonry subcontract to Rascicot no earlier than September 2, and
apparently on September 5. See note 4, supra. Rascicot, therefore, had until
September 10 to execute a subcontract with Callahan. Rascicot pulled out on
September 7.
We are of opinion that the statute raised no bar to the application of Section
44F(4)(c) at that point, because of the prior execution of the general
contract. Section 44F(4)(c) "specifically provides the proper route to
follow where, as here, there is a failure by the selected sub-bidder to execute
a subcontract." Paul Sardella Constr. Co. v. Braintree Hous. Authy., 371
Mass. 235, 241 (1976). See also Paul Sardella Constr. Co. v. Braintree Hous.
Authy., 3 Mass. App. Ct. 326, 330 (1975).9 That route led to substitution of the next masonry
sub-bidder up the line. The only time criterion for substitution prescribed by
Section 44F(4)(c) is that five days must have elapsed after presentation of the
subcontract by the general bidder to the lowest sub-bidder before that
sub-bidder is deemed to have dropped out.
Step-by-step application of the language of Section 44F(4)(c) points to
invocation of the substitution procedure before or after execution of the
general contract. Statutory construction
-------------------------
9 The Sardella cases were decided
under G. L. c. 149, Section 44I(3), which contained text identical to that
which now appears in G. L. c. 149, Section 44F(4)(c).
Page 714
begins with the well-worn maxim that we apply the plain words of the
statute. See Nationwide Mut. Ins. Co. v. Commissioner of Ins., 397 Mass. 416,
420 (1986); Martin v. Rent Control Bd. of Cambridge, 19 Mass. App. Ct. 745, 747
(1985). The conclusion that the substitution process applies after execution of
the general contract finds support in several other provisions of c. 149.
Section 44F, subsection (3), 1st par., provides that "the general contract
executed on the basis of such general bid shall [not] be invalid or rejected
because of the invalidity of such sub-bid . . .; but there shall be
substitution of sub-bidders and adjustment of contract price as if paragraph
(c) of section forty-four F(4) were applicable." If the statute
contemplates postexecution substitution of sub-bidders in that context, there
is no reason to suppose that substitution is prohibited in another -- and
similar -- context. Section 44B(4) allows certain bid deposits of sub-bidders
to be held for five days after execution of the general contract. We may infer
from that provision a legislative assumption that all subcontracts will not
necessarily have been buttoned up on the date the general contract is executed.
What are we to make, then, of the phrase "contingent upon execution of the
general contract" which appears in Section 44F(4)(c)? Considering the
position of the phrase in a fifteen-line sentence and the language we have
mentioned in the statute which contemplates postexecution substitution of
sub-bids, we take the phrase to authorize the execution of subcontracts
contingent upon the contractor executing the general contract. Enabling general
bidders and sub-bidders to do so has considerable utility. It binds the
subcontractor and the subcontractor's bonding company when the general contract
comes into legal existence, and it may avoid just the sort of shortfall which
developed when, as here, the lowest subcontractor in a particular trade fell
away.
Read in this manner, the statute effectuates its apparent design of
substituting for a lapsed lowest bidder the next-to-the-lowest bidder and of
confining the subcontractors to those who have participated in the public
sub-bidding procedure. See Interstate Engr. Corp. v. Fitchburg, 367 Mass. 751,
757-758
Page 715
(1975). At this juncture it is appropriate to wheel up equally trusty canons
of statutory construction: to consider the whole system of which the statute is
a part, Pereira v. New England LNG Co., 364 Mass. 109, 115 (1973); "to
best effectuate the legislative intent, viewing the statute as a whole,"
Tedford v. Massachusetts Hous. Fin. Agency, 390 Mass. 688, 696 (1984); to give
the statute a reasonable construction, School Comm. of Greenfield v. Greenfield
Educ. Assn., 385 Mass. 70, 79-80 (1982); to consider the main object of the
statute, Newbury St. Assoc. v. Assessors of Boston, 386 Mass. 513, 515 (1982);
and to harmonize the troublesome passage, Risk Mgmt. Foundation of the Harvard
Med. Insts., Inc. v. Commissioner of Ins., 407 Mass. 498, 503 (1990).
We are not persuaded by the town's argument that application of the
substitution procedure unreasonably exposes awarding authorities to unexpected
increases in the cost of the project. As we observed in note 8, supra, one way
in which an awarding authority can avoid that risk is to require the successful
bidder to execute subcontracts (for trades as to which sub-bids were filed)
before execution of the general contract. An awarding authority may also
diminish its exposure by retaining bid deposits as long as Section 44B(4)
permits. Had the town done so in this case it would have had Rascicot's $29,750
bid deposit to set against the $66,000 by which Empire's bid exceeded
Rascicot's. Finally, we do not think the town's reliance on JJ Assocs. v. Fall
River Hous. Authy., 19 Mass. App. Ct. 45, 48-51 (1984), is at all cogent. That
case dealt with the right of the public authority to require substitution of a
lower sub-bid at a time when the general contract itself was still contingent
because it was subject to approval by the United States Department of Housing
and Urban Development.
Returning to the questions posed by the single justice, we answer that: (1) the
general contractor and the town are bound to apply the substitution procedure
prescribed in Section 44F(4)(c), notwithstanding the prior execution of the
general contract; and (2) a general contractor is not required by
Page 716
Section 44F(4)(c) to obtain executed subcontracts (with the sub-bidders the
contractor intends to use) prior to the execution of the general contract.
The town and Callahan shall execute a change order increasing the general
contract price by $66,000, and the escrow funds shall be disbursed in
accordance with the order of the single justice and the stipulation of the
parties dated November 14, 1989.
So ordered.
Page 717
END OF DECISION