Court: APPEALS COURT OF MASSACHUSETTS
Citation: 11 Mass. App. Ct. 1009
Parties: E. A. BERMAN COMPANY vs. CITY OF MARLBOROUGH &
another.
Decision Date: April 22, 1981
The plaintiff's subbid on the plumbing work for the city's new high school was
based upon its hope that no-hub pipe would be approved as an item equal to the
more expensive bell and spigot pipe described in the specifications. See G. L.
c. 30, Section 39M(b). The plaintiff
Page 1010
won the contract, and it then sought and obtained from the contractor and the
architectural engineers, in accordance with the procedures detailed in the
specifications, the approval necessary to install no-hub pipe. Notwithstanding
this approval, the city thereafter refused to allow the plaintiff to use no-hub
pipe and required the plaintiff to install the more expensive item. The
plaintiff brought this action to recover the extra cost that it incurred in so
doing, and we affirm the judgment entered in the plaintiff's favor.
1. The city claims that the judgment rewards the plaintiff for conduct which as
a matter of law violated the bidding instructions and the spirit and intent of
G. L. c. 149, Sections 44A-44L. When the plaintiff's employee was preparing the
subbid, he telephoned the project plumbing engineer to do "some casting
about to try and determine if `no-hub' was an equal item to `bell and spigot'
within the terms" of G. L. c. 30, Section 39M(b). The substance of this
conversation is unknown because the city objected to the employee's recitation
of it and the plumbing engineer did not testify. Even assuming, however, that
the conversation involved the plumbing engineer's opinion as to the qualities
of the two types of pipe, it does not follow that the plaintiff acted
wrongfully. The documentary evidence, when viewed with Section 39M(b), shows
that: (a) it was clear from the bidding instructions and specifications that
neither the city nor the architect, nor the architectural engineer could be
bound by the opinion of the plumbing engineer; (b) by preparing its subbid on
the basis of anticipated approval of no-hub pipe as an equal item, the
plaintiff elected to run the risk of disapproval and, thus, of bearing the sole
burden of the extra cost of installing the more expensive item as described in
the specifications; and (c) all the subbidders were free to bid on the same
basis, propose equal items, and run the risk comparable to that of the
plaintiff, and in fact, they may well have done so. See and compare Jack Stone
Co. v. United States, 344 F.2d 370 (Ct. Cl. 1965). This evidence provides a
sound basis for the finding that the conversation did not give the plaintiff a
foot up "in the competition to gain the contract." Interstate Engr.
Corp. v. Fitchburg, 367 Mass. 751, 758 (1975). Commonwealth v. Gill, 5 Mass.
App. Ct. 337, 342-343 (1977).
Moreover, even had the master adopted the city's characterization of the
testimony of the plaintiff's employee as an admission of a bidding advantage,
he would not have been precluded thereby from relying on the documentary
evidence, as he did, to conclude that the plaintiff had not acted wrongfully or
to the disadvantage of other subbidders. See Murphy v. Smith, 307 Mass. 64, 68
(1940); Brown v. Metropolitan Transit Authy., 345 Mass. 636, 638-639 (1963);
Green v. Richmond, 369 Mass. 47, 51 (1975).
2. The plaintiff was not restricted to various work records it may have
possessed as evidence in proving its damages, the extra cost. The city's
reliance on Sylvania Elec. Prod., Inc. v. Flanagan, 352 F.2d 1005 (1st Cir.
1965),
Page 1011
is misplaced. There the contractor's work records were required because without
them the selected method of proving damages constituted a flagrant violation of
the best evidence rule. Here the plaintiff proved its damages through evidence
of computations made by an experienced and qualified plumbing work estimator
who used, in the language of the trade, the "take off" method. This
evidence established the amount of the damages with substantial certainty.
Compare Hetherington & Sons v. William Firth Co., 210 Mass. 8, 21-22
(1911), and White Spot Constr. Corp. v. Jet Spray Cooler, Inc., 344 Mass. 632,
635-636 (1962).
Judgment affirmed.
END OF DECISION