Court: SUPREME JUDICIAL COURT OF
MASSACHUSETTS
Citation: 398 Mass. 476
Parties: CHICOPEE CONCRETE SERVICE, INC. vs. HART ENGINEERING
CO.
County: Suffolk
Hearing Date: September 8, 1986
Decision Date: October 9, 1986
Judges: HENNESSEY, C.J., WILKINS, NOLAN, LYNCH, & O'CONNOR,
JJ.
Where a contract between a general contractor and a subcontractor, under which
the subcontractor was to supply concrete for a public works project, did not
fully incorporate the terms of the general contract, including a clause
providing that all subcontractors were subject to approval by an engineering
firm representing the awarding authority, and where only terms of the general
contract relating to the work to be done were incorporated by general
reference, the engineering firm's refusal to approve the subcontractor did not
justify the general contractor in terminating the subcontract. [477-478] A
general reference clearly stated in a subcontract is sufficient to incorporate
the terms of a general contract, unless incorporation by general reference is
explicitly rejected by statute or regulation. [478] Where the judge in a
contract action should have entered judgment for the plaintiff, rather than for
the defendant, on the basis of the material properly before him on the parties'
cross motions for summary judgment, the Appeals Court, dealing with the same
record on the plaintiff's appeal, was fully warranted in ordering the entry of
summary judgment for the plaintiff. [478] Where the plaintiff on motion for
summary judgment in a contract action presented record support for the
existence of a contract which the defendant had repudiated without right, and
the defendant failed to allege specific facts to establish a genuine triable
issue, summary judgment should have been entered in favor of the plaintiff.
[479]
CIVIL ACTION commenced in the Superior Court Department on September 13,
1979.
Motions for summary judgment were heard by Mel L. Greenberg, J.
Page 477
After review by the Appeals Court, the Supreme Judicial Court granted leave
to obtain further appellate review.
Peter J. Gagne for the plaintiff.
Francis M. Lynch for the defendant.
Robert J. Sherer & James F. Grosso for Associated General Contractors of
Massachusetts, Inc., amicus curiae, submitted relief.
WILKINS, J. The Appeals Court held that the defendant, Hart Engineering Co. (Hart), the general contractor on a public works project in Holyoke, and the plaintiff, Chicopee Contract Service, Inc. (Chicopee), had entered into a contract concerning the supplying of concrete for the project and that Hart was liable for breach of contract when it terminated the contract after the engineering firm representing the city, as was its right, disapproved of Chicopee as a supplier of concrete. Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., 20 Mass. App. Ct. 315 (1985). The Appeals Court thus reversed the summary judgment for Hart entered in the Superior Court, ordered entry of summary judgment for Chicopee on liability, and remanded the case for the determination of damages. Id. at 321. We granted Hart's application for further appellate review, concerned principally with Hart's arguments that (1) the Appeals Court opinion declared that the terms of a general contract could not become part of a subcontract unless those terms were unambiguously restated in the subcontract and (2) the Appeals Court should not have ordered summary judgment for Chicopee on the question of liability. We agree with the Appeals Court's conclusions and shall comment only on the points that attracted our attention in the application for further appellate review. Hart argued, successfully in the Superior Court but unsuccessfully in the Appeals Court, that its contract with Chicopee incorporated by reference the provisions of the prime contract that subcontractors had to be approved by the city's representative and that, because the city's representative disapproved of Chicopee as a supplier of concrete, the subcontract was unenforceable. The problem with Hart's argument is that the terms of the prime contract were not fully incorporated in the
Page 478
subcontract by the language Hart included in the purchase order it gave to
Chicopee, but rather only terms relating to the work to be done were
incorporated by general reference. The Appeals Court was most careful to note
that the terms of a general contract could be incorporated fully in the
subcontract by appropriate reference. Chicopee Concrete Serv., Inc. v. Hart
Eng'g Co., supra at 320. We do not read the Appeals Court opinion as announcing
a rule, as the amicus curiae argues, that a provision of a general contract
will be included in a subcontract only if it is specifically referred to as a
condition of the subcontract. Unless incorporation by general reference is
explicitly rejected by some statute or regulation, incorporation by a clearly
stated general reference will suffice.1 The subcontract could have incorporated the general
terms and conditions of the general contract by cross reference to the relevant
documents. In this case, however, the incorporation was only of those terms of
the general contract that were relevant to the work to be performed by
Chicopee.
Hart complains that the Appeals Court should not have ordered summary judgment
for Chicopee on the issue of liability. If the Superior Court judge should have
entered that judgment on the basis of the material properly before him on the
parties' cross motions for summary judgment, the Appeals Court dealing with the
same record is fully warranted in directing that it be done. See 6 Moore's
Federal Practice par. 56.27 [2] (2d ed. 1985).We see no genuine issue as to any
material fact which would bar the award of summary judgment on the liability
question. Hart did not argue below that, if there was a contract in which the
owner-approval clause was not incorporated by reference, Chicopee knew, or at
least had notice, of the owner-approval
-------------------------
1 The Appeals Court found
reinforcement in its conclusion from the presence in the subcontract of the
requirement "to fully comply with all the requirements pertaining to
Nondiscrimination in Employment and the President's Executive Order 11246 and
amendments." Id. at 321. It appears that by regulation these requirements
may not be incorporated by reference to the contract documents (29 C.F.R.
Section 5.5[a] [6] [1986]), and thus the explicit, special reference to those
requirements seems to provide no reinforcement to the Appeals Court's
conclusion.
Page 479
requirement and thus should be bound by the owner's disapproval. If it were
supported by the record, we could consider this argument in support of the
result reached in the trial court, even though Hart did not raise the issue
there and the judge did not deal with it. 10 C.A. Wright & A.R. Miller,
Federal Practice and Procedure Section 2716, at 658 (1983 & Supp.
1986).2 The record, however, does not
support it. Chicopee presented record support for the existence of a contract
which Hart had repudiated without right. In the circumstances, to avoid partial
summary judgment against it the burden was on Hart to present record support
for its position that Chicopee knew of, or at least had notice of, the
owner-approval requirement before the subcontract was entered into. It did not,
and understandably so, because Hart was not relying on this theory at the trial
level. "[I]f the moving party shows that there is no issue for trial, the
opposing party must respond and allege specific facts which establish that
there is a genuine, triable issue, or summary judgment (if appropriate in all
other respects) will be entered against him." Community Nat'l Bank v.
Dawes, 369 Mass. 550, 554 (1976). The judgment is reversed. Summary judgment
for Chicopee on liability is to be entered, and the question of damages for
breach of contract shall be considered. So ordered.
-------------------------
2 The Appeals Court "assumed for
purposes of deciding this case that Chicopee did not have actual knowledge of
the owner-approval clause," and thus that court did not consider whether
the existence of such knowledge would call for entry of judgment for Hart.
Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., supra at 321 n.7. The Appeals
Court appears to have made the assumption that Chicopee had no knowledge of the
owner-approval clause on a rather cryptic statement of Chicopee's president in
an affidavit that at a time after the subcontract was entered into he did not
know of "`any engineer or owner action on Chicopee.'" See id. We do
not credit this statement as an affirmative showing that Chicopee was not on
notice and did not know of the owner-approval provision in the general
contract.
End Of Decision
Court: APPEALS COURT OF MASSACHUSETTS
Citation: 20 Mass. App. Ct. 315
Parties: CHICOPEE CONCRETE SERVICE, INC. vs. HART ENGINEERING
CO.
County: Suffolk
Hearing Date: February 6, 1985
Decision Date: July 3, 1985
Judges: PERRETTA, KAPLAN, & DREBEN, JJ.
Correspondence between a general contractor and a supplier of concrete who, at the request of the general contractor, had submitted prices which the contractor used in preparing its bid on a public works project warranted the conclusion that there was an enforceable contract for the supply of concrete for the project between the general contractor and the supplier. [317-319] Where a contract between a general contractor and a subcontractor under which the subcontractor was to supply concrete for a public works project did not incorporate the general contract in its entirety and did not specifically incorporate a clause of the general contract providing that all subcontractors were subject to approval by an engineering firm representing the awarding authority, the engineering firm's refusal to approve the subcontractor did not justify the general contractor in terminating the subcontract. [319-321]
CIVIL ACTION commenced in the Superior Court Department on September 13,
1979.
Motions for summary judgment were heard by Mel L. Greenberg, J.
Peter J. Gagne for the plaintiff.
Francis M. Lynch, for the defendant.
PERRETTA, J. The defendant (Hart) was awarded a contract by the city of
Holyoke for the construction of a waste water treatment plant. In preparing its
bid, Hart used prices for concrete that had been submitted to it by the
plaintiff (Chicopee), a concrete supplier and Hart's proposed subcontractor.
The general conditions of the contract between the city and Hart provided that
all subcontracts were subject to the approval of
Page 316
the engineering firm (Tighe & Bond/SCI, hereinafter Tighe) representing
the city. When approval of Chicopee was not given, Hart selected another
subcontractor, and Chicopee brought this action for breach of contract against
Hart. Both parties moved for summary judgment; Chicopee's motion was limited to
the issue of liability. The judge concluded that, although there was a valid
contract between Chicopee and Hart, that contract was subject to approval by
the city's engineering firm. Because approval was denied, Hart did not
wrongfully terminate the contract. We conclude that the approval clause in the
prime contract was not made a part of the enforceable contract between Hart and
Chicopee and reverse the judgment.
I. The Undisputed Facts.
In preparing its bid for the city's construction project, Hart requested
Chicopee's price quotations for cement. By letter to Hart, dated September 12,
1978, Chicopee quoted its prices which, in turn, were used by Hart in
calculating its bid on the project. On November 2, 1978, Hart directed a letter
to Chicopee which contained three statements here important:
(1) "This will confirm our intention to award the purchase order for the
following: . . . [list of concrete mixes and prices]."
(2) "This award will be subject to our receiving a formal contract from
the proper awarding authorities."
(3) "Your attention is directed to the Contract & General Conditions,
Supplementary General Conditions, Special Conditions, Information for Bidders,
and the Technical Specifications which will be made a part of your purchase
order. You are specifically cautioned to fully comply with all the requirements
pertaining to Nondiscrimination in Employment and the President's Executive
Order 11246."
Page 317
In anticipation of working on the project, Chicopee expanded its facilities
and purchased new equipment. The city awarded Hart the prime contract on
December 20, 1978, and on January 25, 1979, Hart sent its purchase order to
Chicopee, the first paragraph of which reads, in pertinent part: "Furnish
all materials and equipment to perform the `SCOPE OF WORK' hereto attached in
strict accordance with plans and specifications entitled `Holyoke Wastewater
Treatment Plant Improvements' . . . as prepared by Tighe & Bond/SCI,
including all drawings listed therein . . . General Terms & Conditions,
codes, and other publications referred to therein." Chicopee added
qualifications to two of the terms of the purchase order,1 which it then signed and delivered to Hart,
along with the usual and necessary bonds, on March 19, 1979. At that time,
Chicopee was unaware that four days earlier, March 15, 1979, Tighe had rejected
Hart's proposal to use Chicopee as the concrete supplier. Hart withdrew its
purchase order to Chicopee on March 21, 1979.
II. The Hart-Chicopee Contract.
The judge concluded that "[a]n enforceable contract was formed"
between Chicopee and Hart "upon the issuance" of Hart's purchase
order of January 25, 1979. We agree with this conclusion and the following
reasoning upon which it rests.
A subcontract for the sale of concrete is controlled by G. L. c. 106, the
Uniform Commercial Code. See Mishara Constr. Co. v. Transit-Mixed Concrete
Corp., 365 Mass. 122, 124 (1974). Section 2-204(1), inserted by St. 1957, c.
765, Section 1, provides: "A contract for sale of goods may be made in any
manner sufficient to show agreement, including conduct by both parties which
recognizes the existence of such a contract."
-------------------------
1 Hart required that Chicopee employ
workers who "can work in harmony with all other" workers on the
project. To this Chicopee agreed, except for the "signing of a new Union
Contract other than that we already have." The purchase order also
provided that Chicopee's prices were to remain "firm through life of
project" and were to be discounted $.60 per cubic yard. Chicopee accepted
the discount but limited it to "for payment 15th prox. only" (which
we construe to mean if paid within a certain time) and also limited
"firm" prices only through 1980.
Page 318
Chicopee, on September 12, 1978, in response to a request from Hart, had
submitted a price list which Hart used in preparing its bid on the prime
contract. Hart advised Chicopee on November 2, 1978, that it intended to award
Chicopee the purchase order if it were awarded the contract by the city. In
anticipation of the purchase order, Chicopee expanded its facilities. "An
offer is made when the offeror leads the offeree to reasonably believe that an
offer has been made. Timmins v. F. N. Joslin Co., 303 Mass. 540 . . . (1939).
Kuzmeskus v. Pickup Motor Co., 330 Mass. 490 . . . (1953)." Gilbert &
Bennett Mfg. Co. v. Westinghouse Elec. Corp., 445 F. Supp. 537, 545 (D. Mass.
1977). Thus, Chicopee's price list was accepted by Hart, see Loranger Constr.
Corp. v. E. F. Hauserman Co., 376 Mass. 757, 762 (1978) (use of one's estimate
by another in submitting a bid can constitute acceptance of an offer, even
without notification to the offeror), and there was, as of November 2, 1978, at
the very least, an agreement subject to the drafting of the purchase order,
that is, a "formal memorial of the terms."2 Nigro v. Conti, 319 Mass. 480, 482 (1946). See also Sands
v. Arruda, 359 Mass. 591, 594 (1971).
Hart relies upon various cases3 to argue
that the letters of September 12 (Chicopee's price list) and November 2 (Hart's
response) were mere steps in the negotiation process. However, a reading of
those cases shows them to be distinguishable on the basis of the writings
therein involved and the conduct of the parties in light of the writings.
Moreover, even were we to view Hart and Chicopee's letters and conduct as mere
negotiation, we would nonetheless conclude that Hart's purchase order
constituted a valid contract. See Mishara Constr. Co. v. Transit-Mixed Concrete
Corp., 365 Mass. at 124. Hart argues that, because Chicopee changed the terms
of the purchase order, see note 1, supra, there was
-------------------------
2 Hart argues that its letter of November 2, 1978, was at best "a step in the negotiations looking to the issuance of Hart's purchase order."
3 Interstate Indus., Inc. v. Barclay Indus.,
Inc., 540 F.2d 868 (7th Cir. 1976). Cannavino & Shea, Inc. v. Water Works
Supply Corp., 361 Mass. 363 (1972). Tull v. Mr. Donut Dev. Corp., 7 Mass. App.
Ct. 626 (1979).
Page 319
no acceptance by Chicopee, and hence, no contract. As we read G. L. c. 106,
Section 2-207(1) and (2),4 Chicopee's
insertions only raise the question whether those terms become parts of the
contract between Hart and Chicopee. See Leonard Pevar Co. v. Evans Prod. Co.,
524 F. Supp. 546, 549-552 (D. Del. 1981); Gard Industrial Plastics, Inc. v.
Aubrey Mfg., Inc., 103 Ill. App. 3d 380, 385-386 (1982). See also 2 Anderson,
Uniform Commercial Code Section 2-207:12 (3d ed. 1982). Although that question
may or may not be relevant to the issue of damages (keeping in mind the nature
of Chicopee's insertions and the fact that the contract was repudiated before
performance commenced), it does not alter the fact that there was a valid
contract between Hart and Chicopee.
III. The Breach.
Whether Hart was justified in withdrawing its purchase order after Tighe
rejected Chicopee as a concrete supplier turns on whether the owner-approval
clauses5 of the prime contract had been
made part of the contract between Hart and Chicopee.
-------------------------
4 Sections 2-207(1) and (2), inserted
by St. 1957, c. 765, Section 1, provide:
"(1) A definite and seasonable expression of acceptance or a written
confirmation which is sent within a reasonable time operates as an acceptance
even though it states terms additional to or different from those offered or
agreed upon, unless acceptance is expressly made conditional on assent to the
additional or different terms.
"(2) The additional terms are to be construed as proposals for addition to
the contract. Between merchants such terms become
part of the contract unless:
(a) the offer expressly limits acceptance to the terms of the offer;
(b) they materially alter it; or
(c) notification of objection to them has already been given or is given within
a reasonable time after notice of them is
received."
5 Hart points to three clauses in the
first of the two volume "Specifications For Construction" of the
project which require that subcontracts be conditioned upon Tighe's approval.
Paragraph G of the "Proposal Form for Sub Bid" provides that the
subbidder "agrees to be bound to the General Contractor by the terms of
the hereinbefore Plans, Specifications (including all general conditions stated
therein), and addenda, and to assume toward him all the obligations and
responsibilities that he, by those documents, assumes toward the owner."
Article 58 of the "General Requirements" and paragraph HH of the
"Special Provisions" provide that the contractor cannot
"sublet" any of the work without prior written consent of the
owner.
Page 320
The judge concluded that the purchase order "effectively incorporated
the provisions of the prime contract in the subcontract."6 We do not agree.
In the absence of unambiguous and appropriate language in the purchase order
incorporating either the owner-approval clause or the prime contract in its
entirety, all that is impliedly incorporated into the subcontract is the
obligation of the subcontractor to perform as the general contractor is bound
to do "in relation to the particular part of the work to be
performed." Vappi & Co. v. Sullivan, 331 Mass. 463, 467 (1954). See
John Soley & Sons v. Jones, 208 Mass. 561, 566-567 (1911).
If there was wholesale incorporation of the terms of the prime contract into
the purchase order, it must be by reason of the purchase order's proviso that
Chicopee was to "[f]urnish all materials and equipment required to perform
the `SCOPE OF WORK' . . . in strict accordance with plans and specifications
[of the prime contract], including . . . [the] General Terms and Conditions . .
. ." We do not see in this language, notwithstanding the reference to the
"General Terms and Conditions" and, hence, art. 58, as well as
paragraph HH of art. 80 of the "Special Conditions," anything other
than an incorporation of those terms of the prime contract which are germane to
the work to be performed by the subcontractor in behalf of the contractor. See
Frederick Raff Co. v. Murphy, 110 Conn. 234, 240 (1929) ("The securing of
the consent of the engineers in charge of the work to the making of the
contract between the parties, as required by the specifications, was not made
an express condition of that contract nor are facts found from which a
condition could be implied in fact"). Compare Farm-Rite Implement Co. v.
Fenestra, Inc., 340 Mass. 276, 281 (1960), S.C., 342 Mass. 427, 431 (1961),
where the cross
-------------------------
6 The parties have not argued, and we
have not considered, the applicability of G. L. c. 149, Section 44D, as in
effect in 1979, to this controversy.
Page 321
references in the various documents were held to give rise to incorporation
of the prime contract clause in question.7
Our conclusion that the prime contract had not been incorporated in its
entirety is reinforced by the fact that part of the prime contract which was
not particular to the work to be performed was incorporated into the purchase
order by express and unambiguous language: "You are specifically cautioned
to fully comply with all the requirements pertaining to Nondiscrimination in
Employment and the President's Executive Order 11246 and amendments." The
approval by Tighe of Hart's use of Chicopee as the concrete supplier for the
project was not a condition of the contract between Hart and Chicopee. Hart's
inability to obtain Tighe's approval of Chicopee did not immunize Hart from
liability to Chicopee for breach of contract.
IV. Conclusion.
It follows from what we have said that the judgment is reversed. Summary
judgment on Chicopee's limited motion is to enter, and the matter is to stand
for further proceedings on the question of damages.
So ordered.
-------------------------
7 We are not unmindful of the fact
that on February 15, 1979, Tighe wrote to Hart requesting further information
bearing upon Chicopee's ability to perform the required work, that Hart
forwarded that letter to Chicopee with a request that the information be
furnished, and that on February 27, 1979, Chicopee provided the requested
information to Hart. Even assuming that the letter lends itself to an inference
that Chicopee was thereby put on notice that owner approval was part of the
prime contract, an affidavit signed by Chicopee's president specifically denies
knowledge of "any engineer or owner action on Chicopee." Hart's
affidavit is silent on the issue of actual notice to Chicopee. Compare JJ
Associates, Inc. v. Fall River Housing Authy., 19 Mass. App. Ct. 45, 46-47,
50-51 (1984). Additionally, we note that in its answer Hart admitted that on
March 13, 1979, it notified Chicopee that if the purchase order of January 25,
1979, and a satisfactory performance bond were not received by Hart by March
19, 1979, the purchase order would be "null and void."
As it is assumed for purposes of deciding this case that Chicopee did not have
actual knowledge of the owner-approval clause, we need not consider whether
such knowledge would be relevant to the question whether Chicopee was thereby
bound irrespective of incorporation of the prime contract in the purchase
order.
Page 322
END OF DECISION