Court: APPEALS COURT OF MASSACHUSETTS
Citation: 24 Mass. App. Ct. 506
Parties: B. J. HARLAND ELECTRICAL CO., INC. vs. GRANGER BROTHERS, INC.,
& another.1
County: Suffolk
Hearing Date: March 16, 1987
Decision Date: July 21, 1987
Judges: PERRETTA, KAPLAN, & WARNER, JJ.
In an action brought by a subcontractor on a public works project against the general contractor and its surety alleging that the general contractor had failed to perform its work in an orderly manner and to coordinate the project's work so that the plaintiff could perform its work by the contract completion date and that, as a result of such failure, the plaintiff incurred additional expenses in having to perform its work piecemeal, out of sequence, and in winter weather, it was held that the plaintiff was not entitled to recover such additional expenses, where those expenses constituted hindrance or delay damages, recovery of which was precluded by the terms of its subcontract, and where there was nothing in those portions of the contract incorporating the language of G. L. c. 149, Sections 44C and 44I (3), as in effect prior to St. 1980, c. 579, Section 55, which would have given the plaintiff the right to seek damages for hindrances or delays. [509-514]
CIVIL ACTION commenced in the Superior Court Department on November 15,
1982.
The case was heard by Haskell C. Freedman, J., sitting under statutory
authority.
John F. Hurley, Jr., for the defendants.
Joseph A. Pisarri for the plaintiff.
PERRETTA, J. This appeal arises out of an action brought under the public works payment bond statute, G. L. c. 149,
-------------------------
1 United States Fidelity and Guaranty
Company, which, with Granger Brothers, Inc., filed a third-party complaint
against the Commonwealth and its architect. That complaint was severed from the
present action and is pending. The present judgment was entered pursuant to
Mass.R.Civ.P. 54(b), 365 Mass. 821 (1974).
Page 507
Section 29 (as amended through St. 1972,c. 774, Section 5), by the plaintiff
subcontractor (Harland) against the defendant general contractor (Granger) and
its surety (Fidelity). Harland alleged that Granger had failed to "begin,
perform and complete its work in an orderly manner" and to "supervise
and coordinate all the project work so that Harland [, in turn,] could perform
its work in an orderly manner" and by the contract completion date.
Harland alleged that, as a result of Granger's failures, Harland incurred
expenses above the contract price for which, by this action, it sought recovery
on the bond. Judgment entered against Granger and Fidelity, "jointly and
severally." We conclude that the expenses sought by Harland are delay
damages and that recovery of such damages is precluded by the terms of its
subcontract. We reverse the judgment, and remand the matter for a recalculation
of the amount otherwise due Harland.
I. The Facts.
We recite the facts as they were found by the trial judge under Mass.R.Civ.P.
52(a), 365 Mass. 816 (1974). In 1978, the Commonwealth, through its Bureau of
Building Construction, solicited bids for the construction of a campus center
at Holyoke Community College. Granger was selected as the general contractor,
and it entered into a subcontract with Harland, the lowest qualified bidder,
for the electrical work. That contract price was $257,760. Fidelity, as surety
for Granger, issued a payment bond, as required by G. L. c. 149, Section 29.
It was originally planned that the building, to be of poured concrete, would be
constructed "horizontally," that is, from the ground upwards, floor
by floor. Work began in the summer of 1978, and while excavating for the
foundation, Granger ran into ledge. Rather than clearing the ledge, Granger
abandoned the "horizontal" plan for the season and continued to build
upward over that portion of the site that it had been able to prepare, later
extending each floor as the ledge was removed. Harland, which had to install
conduits to carry wiring inside the floors, walls, and ceilings as they were
poured, was required to follow Granger in this new construction sequence.
As a consequence of this change, Harland's efficiency was adversely affected.
Its workers were forced to work piecemeal,
Page 508
moving from place to place as work became available rather than proceeding
in an orderly sequence.
There were other problems. Granger poured ceilings which the architect deemed
unacceptable and for which he demanded corrections. Eight months elapsed while
the matter was disputed. It was resolved when Granger undertook remedial
patching and painting. In the meantime, however, Harland could not install
ceiling-mounted light fixtures. When the remedial work was done, Harland's
electricians could not use a rolling scaffold to hang lights because by then
the interior walls had been poured. Consequently, the electricians had to erect
and dismantle fixed scaffolding in each room. Further, a template could not be
used to mark the ceilings where drilling was to be done to connect the
fixtures, as the template scratched the paint that Granger had to apply in
doing the remedial work. The drill holes thus had to be measured and marked by
hand.
Harland's efficiency was further hampered by the fact that Granger did not have
enough concrete forms, which reduced the amount of concrete that could be
poured at any one time. During the winter, Granger provided heat only in those
areas where it was pouring concrete. Harland's employees often had to work in
cold, and sometimes unenclosed, areas, decreasing their efficiency and slowing
their progress.
Onsite problems arose with frequency. Without going into detail, some of the
problems were caused by errors, omissions, or conflicts in the project plans
and specifications. The time problem was exacerbated as solutions were sought
and decisions were made. Throughout construction, Harland's president and
Granger's job superintendent frequently discussed the progress of the project.
The job superintendent indicated that Granger intended to present a claim for
delay costs and that Harland could submit its damages with that claim. Granger,
however, went out of business without having pursued its or Harland's claims.
Harland's claim is that it substantially completed its work by the end of
October, 1980, some nine months later than the originally scheduled completion
date. Granger paid Harland
Page 509
$298,148.23,2 but Harland claims that
it was owed $347,798.20, the amount due for the contract work plus the fair
market value of the extra labor and materials, leaving a balance owed of
$49,649.97. The trial judge found that, because of the numerous previously
described events, Harland had incurred increased labor costs (caused by reduced
productivity and periodic wage increases to its workers) and overhead expenses
subsequent to the scheduled completion date of its work on the contract. He
entered a judgment for Harland in the amount of $44,860.97, plus interest. The
judgment was thereafter amended to include legal fees for Harland in the amount
of $15,500.
II. The Contract.
Article XXIII of the general conditions of the prime contract which was
incorporated in the subcontract, reads: "DELAYS. Except as otherwise
provided by law the contractor shall not be entitled to damages on account of
any hindrances or delays, avoidable or unavoidable; but if such delay be
occasioned by the awarding authority, the contractor may be entitled to an
extension of time only, in which to complete the work, to be determined by the
designer."3 It is well established
in Massachusetts that a contract provision such as art. XXIII is enforceable
and precludes an award of damages on account of delay. See Charles I. Hosmer,
Inc. v. Commonwealth, 302 Mass. 495, 499-501 (1939); Coleman Bros. v.
Commonwealth, 307 Mass. 205, 215-216 (1940); Charles T. Main, Inc. v.
Massachusetts Turnpike Authy., 347 Mass. 154, 162-163 (1964); Wes-Julian
Constr. Corp. v. Commonwealth, 351 Mass. 588, 594-597 (1967); Joseph E. Bennett
Co. v. Commonwealth, 21 Mass. App. Ct. 321, 329-330 (1985).
-------------------------
2 The components of this amount are as
follows: the contract price of $257,760, plus the cost of extra work and
materials ordered by Granger in the amount of $41,314.20, less an amount of
$925.97 which, however, Granger admitted at trial was still owing.
3 Article XXIII also sets out the
provisions of G. L. c. 30, Section 39O, which describes those conditions under
which a contractor or subcontractor may recover damages for delay. See part III
of this opinion, infra.
Page 510
Harland argues that art. XXIII is not applicable to its claim because it is
not seeking damages for delay; rather, it wants the "increased cost of
performing its work piecemeal, out of sequence and in winter weather, which
conditions are the direct result of Granger's failure to begin, prosecute, and
complete its work in an orderly manner and to provide winter heat and weather
protection." If Harland's claim is not based upon delay, then it appears
to us that Harland is seeking damages for hindrances. See, e.g., John E. Green
Plumbing & Heating Co. v. Turner Constr. Co., 742 F.2d 965, 966-967 &
n.3 (6th Cir. 1984). There the contractor successfully argued that delay
damages referred only "to the cost of an idle workforce" whereas its
extra expenses were incurred as a result of hindrances, e.g., "failure to
properly coordinate work on the project and failure to ensure that temporary
heat was provided." In accepting the contractor's distinction, the court
relied heavily on the fact that the contract there in issue precluded damages
only on account of delay rather than the commonly used language of "delay
or hindrance" (emphasis in original). Id. at 967. In other cases relied
upon by Harland where the contract precluded delay damages but recovery was
nonetheless allowed, the awards were based upon conduct found to constitute
active interference. See, e.g., Blake Constr. Co. v. C.J. Coakley Co., 431 A.2d
569, 579 (D.C. 1981); De Riso Bros. v. State, 161 Misc. 934, 940-942 (N.Y. Ct.
Cl. 1937).
In the present instance, any distinction between delay and hindrance damages is
one without a difference. The contract speaks to both, "hindrance or
delays," bringing Harland's claims squarely within the preclusive terms of
art. XXIII. See the judgments against the claimants in: Coleman Bros. v.
Commonwealth, 307 Mass. at 216 (faulty plans, indecision, unreasonable delays
in ordering extra work); Charles T. Main, Inc. v. Massachusetts Turnpike
Authy., 347 Mass. at 162-163 (delays resulting from extensions of time to
contractors); Wes-Julian Constr. Corp. v. Commonwealth, 351 Mass. at 596-597
(unreasonable delay in arranging for removal of utilities from site); Joseph E.
Bennett Co. v. Commonwealth, 21 Mass. App.
Page 511
Ct. at 329-330 (failure to coordinate and control work). Additionally,
Harland's claims are not based upon any allegations of arbitrariness or
intentional wrongdoing by Granger. See and compare Farina Bros. v.
Commonwealth, 357 Mass. 131, 138-139 (1970), with Joseph E. Bennett Co. v.
Commonwealth, 21 Mass. App. Ct. at 330.
III. Applicability of Art. XXIII.
In reliance upon the prefatory language to the preclusive terms of art. XXIII,
"[e]xcept as otherwise provided by law," Harland argues that its
right to recover on its claim is provided for by G. L. c. 149, Sections 44C and
44I(3), as in effect prior to St. 1980, c. 579, Section 55.4 Section 44C mandated that public works construction
contracts contain a provision requiring the general contractor to install
weather protection in work areas and to "furnish adequate heat in the area
so protected during the months of November through March." Section 44I(3)
required that the following language appear in contracts for public works
construction: "The contractor agrees to begin, prosecute and complete the
entire work specified by the Awarding Authority in an orderly manner so that
the subcontractor will be able to begin, prosecute and complete the work
described in this subcontract." Although these mandated clauses do not
appear within art. XXIII, they are elsewhere appropriately included in the
contract.
Article XXIII does contain, verbatim, the language of G. L. c. 30, Section 39O,
inserted by St. 1973, c. 1164,5 This
required statutory language immediately follows the no delay damages
-------------------------
4 See now G. L. c. 149, Sections
44F(1) and 44F(4)(c), containing language identical in substance to the
sections cited in the text.
5 This statute, which appears in full in
art. XXIII, provides:
"Every contract subject to the provisions of section thirty-nine M of this
chapter or subject to section forty-four A of chapter one hundred forty-nine
shall contain the following provisions (a) and (b) in their entirety and, in
the event a suspension, delay, interruption or failure to act of the awarding
authority increases the cost of performance to any subcontractor, that
subcontractor shall have the same rights against the general contractor for
payment for an increase in the cost of his performance as provisions (a) and
(b) give the general contractor against the awarding authority, but nothing in
provisions (a) and (b) shall in any way change, modify or alter any other
rights which the general contractor or the subcontractor may have against each
other.
(a) The awarding authority may order the general contractor in writing to
suspend, delay, or interrupt all or any part of the work for such period of
time as it may determine to be appropriate for the convenience of the awarding
authority; provided, however, that if there is a suspension, delay or
interruption for fifteen days or more or due to a failure of the awarding
authority to act within the time specified in this contract, the awarding
authority shall make an adjustment in the contract price for any increase in
the cost of performance of this contract but shall not include any profit to
the general contractor on such increase; and provided further, that the
awarding authority shall not make any adjustment in the contract price under
this provision for any suspension, delay, interruption or failure to act to the
extent that such is due to any cause for which this contract provides for an
equitable adjustment of the contract price under any other contract provisions.
(b) The general contractor must submit the amount of a claim under provision
(a) to the awarding authority in writing as soon as practicable after the end
of the suspension, delay, interruption or failure to act and, in any event, not
later than the date of final payment under this contract and, except for costs
due to a suspension order, the awarding authority shall not approve any costs
in the claim incurred more than twenty days before the general contractor
notified the awarding authority in writing of the act or failure to act
involved in the claim."
Page 512
clause of art. XXIII. As we read art. XXIII, it allowed Harland to seek "payment for an increase in the cost of. . . [its] performance," G. L. c. 30, Section 39O, provided the increase could be attributed to those causes set out in Section 39O, and that the additional payment was sought in the manner therein prescribed.6 Harland advises us in its brief, however, that it "does not claim under that statute."7
-------------------------
6 Also, art. XXII of the contract sets
out, verbatim, the language of G. L. c. 30, Section 39N, inserted by St. 1972,
c. 774, Section 4 which is comparable to Section 39O, and which provides, in
pertinent part: "If, during the progress of the work, the contractor or
the awarding authority discovers that the actual subsurface or latent physical
conditions encountered at the site differ substantially or materially from
those shown on the plans or indicated in the contract documents either the
contractor or the contracting authority may request an equitable adjustment in
the contract price of the contract applying to work affected by the differing
site conditions."
7 Statements in Harland's brief
concerning its right to seek delay damages under Section 39O, as incorporated
in art. XXIII, are somewhat contradictory. Harland first states that it makes
no claim under Section 39O. Later, Harland argues that, "because it had no
privity" with the Bureau of Building Construction, it could seek damages
only from the defendants who, by their third-party complaint, can "recoup
whatever damages Harland may recover" in the present action. Later still,
Harland contends that, "even if" its claim "were somehow
construed to be a `delay claim,' the defendants would nevertheless be entitled
to relief" under Section 39O in the third-party action. Next, in support
of the defendants' right to indemnification for any delay damages recovered by
Harland, Harland argues that Section 39O allows for delay damages in instances,
such as the present, where the delay is due to reasons other than an order by
the awarding authority to the general contractor "to suspend, delay, or
interrupt all or any part of the work. . ." Section 39O.
Page 513
There was nothing in G. L. c. 149, Sections 44C and 44I(3) (see note 4,
supra), or in the contract which expressly provided for a remedy in the event
of a breach of those statutory obligations by Granger. That is not to say,
however, that Harland was at Granger's mercy. It was open to Harland to take
the position that Granger's failures were sufficiently egregious to excuse
Harland from further performance of its duties under the contract and to seek
recovery for any damages caused by Granger's breach. See Quintin Vespa Co. v.
Construction Serv. Co., 343 Mass. 547, 554 (1962); Ward v. American Mut. Liab.
Ins. Co., 15 Mass. App. Ct. 98, 100-101 (1983).
Harland does not here seek reimbursement for any labor and materials that it
furnished beyond what were called for by the contract. Compare Richardson Elec.
Co. v. Francese, 21 Mass. App. Ct. 47 (1985); Joseph E. Bennett Co. v.
Commonwealth, 21 Mass. App. Ct. at 326-329. Rather, all its claims are based
upon a decrease in its efficiency as a result of a lack of heat, inaccurate
construction plans and specifications,8
and having to perform its work out of sequence, and the trial judge found to
that effect.
We must construe the contract as a whole. "Contracts are made to be
performed, and it must be held that the parties intended to enter into a
complete and final arrangement under
-------------------------
8 Harland claims that Granger can be
held accountable to it for the defective plans and specifications on the
authority of John F. Miller Co. v. George Fichera Constr. Corp., 7 Mass. App.
Ct. 494, 499 (1979), and Richardson Elec. Co. v. Francese, 21 Mass. App. Ct. at
52. Those cases hold that a contractor may be liable to a subcontractor for an
"omission, inconsistency, or discrepancy" in plans and specifications
which is "obvious" to the contractor who nonetheless uses the plans
and specifications "to secure a secondary level of bids." Ibid.
Page 514
such terms and conditions as would create and define their obligations and
would enable them to accomplish their contemplated aims and objects. With this
end in view, every phrase and clause must be presumed to have been designedly
employed, and must be given meaning and effect, whenever practicable, when
construed with all the other phraseology contained in the instrument, which
must be considered as a workable and harmonious means for carrying out and
effectuating the intent of the parties." Charles I. Hosmer, Inc. v.
Commonwealth, 302 Mass. at 501. Reading the contract as a harmonious and
workable whole, we find nothing in those portions of the contract incorporating
the language of G. L. c. 149, Sections 44C and 44I(3), which gives Harland the
right to seek damages for hindrances or delays. The right to recover damages
for hindrances or delays is comprehensively provided for by art. XXIII (and,
perhaps art. XXII, see note 6, supra), subject to the limitations therein
contained and agreed to by Harland when it signed the contract. That article is
enforceable and binding upon Harland.
IV. Conclusion.
It follows from what we have said that we need not consider the defendants'
argument that delay damages cannot be recovered under the payment bond issued
pursuant to G. L. c. 149, Section 29. However, Granger admitted at trial, and
Fidelity does not dispute, that there is money due and owing Harland on the
contract. See note 2, supra. Payment of that amount is guaranteed by the bond
and is properly recovered in an action brought under Section 29. Accordingly,
the judgment is vacated, and the case is remanded to the Superior Court, where
a new judgment for Harland shall be entered in an amount of $925.97, plus
interest and counsel fees, which must be recalculated. Costs of appeal are not
to be awarded to any party.
So ordered.
End of Decision.